Delta Forge 2
Buildout Tracker (beta): Applied Digital's Delta Forge 2 in Brookwood, Ala., carries a 210 MW, $5.2 billion hyperscaler lease and a stated $3.2 billion investment, but no county or city record of its incentive deal is posted and no Alabama Power contract petition has reached state regulators.
Delta Forge 2
On June 8, 2026, Applied Digital Corp. said it had signed a 15-year lease for 210 MW of critical IT load at Delta Forge 2, its fifth AI Factory campus, with a U.S.-based, high investment-grade hyperscaler it did not name. It said only that the campus was in “a new southern state.” The company put base-term contracted revenue at about $5.2 billion, or about $12.7 billion if all renewal options are exercised over a 30-year total term, and said initial operations were expected to begin in the first quarter of 2028. Its quarterly report for the period ended Aug. 31 says the lease was entered into on June 5 and carries three five-year renewal options.
On Sept. 24, Applied Digital named Brookwood, in Tuscaloosa County, Ala., as the site. The company said it and its tenant will invest more than $3.2 billion in a campus of about 1.26 million square feet on roughly 160 acres of a nearly 1,300-acre site, with construction employment peaking above 1,000 workers, more than 100 full-time employees and operations expected to begin in 2028. It said it will pay $270 million in community benefit payments over 20 years to the Tuscaloosa County Economic Development Authority, to be shared by Brookwood, Tuscaloosa, Northport, Tuscaloosa County, the Tuscaloosa County Road Improvement Commission and DCH Health System, whose local taxes are being abated, in addition to about $131.5 million in education taxes over the same period. The release did not state the amount of the abatements. It said the campus will use closed-loop cooling and that Applied Digital will pay the full cost of serving its energy needs so the cost is not shifted to other Alabama Power customers. No county authority, county commission or city record of the incentive agreement had been posted online as of Nov. 6.
Applied Digital’s Oct. 7 results release lists Delta Forge 2 in Alabama among campuses in various stages of construction. Its quarterly report describes the campus as a single building under construction, with expected delivery in the first half of calendar 2028. No project financing for the campus has been disclosed. Under Act 2026-610, which took effect Oct. 1, the Alabama Public Service Commission reviews utility contracts with data centers of 150 MW or more. In an October order in Docket 33709, the PSC required Alabama Power to file a public petition for each contract naming the customer, its parent entities, the location and the maximum contracted capacity, and said a petition is deemed approved if the commission does not vote within 90 days. The PSC’s recent filings list, checked Nov. 6, showed no petition naming Applied Digital or Brookwood. The Alabama Department of Environmental Management’s Tuscaloosa County page lists an air permit application received for “Applied Digital Corporation Brookwood Forge1” on Brookwood Parkway; it lists no issued permit for the site.
Project status
Tracker update: Nov. 6, 2026Status board
$5.2B base-term lease. More than $3.2B investment stated by the company. No project financing disclosed.
ADEM air permit application received. No PSC petition found. No county or city record of the incentive agreement posted.
No lawsuit, petition or formal objection found in state records.
No schedule change or tenant exit in company filings. Operations still targeted for 2028.
Stage gauge
- 1Lease signed210 MW, 15 years, June 5, 2026
- 2Site namedBrookwood, Sept. 24, 2026
- 3Local incentivesDescribed by company; no public record
- 4State permitsADEM air application received
- 5PSC power contractNo petition found
- 6Project financingNot disclosed
- 7Construction10-Q: single building under construction
- 8OperationsTarget: 1H 2028
Lease value vs. stated investment ($B)
term (15 yrs)
renewals (30 yrs)
investment
Land (acres)
By the numbers
pending
ADEM’s Tuscaloosa County page lists an air permit application received for “Applied Digital Corporation Brookwood Forge1,” Brookwood Industrial, Brookwood Parkway. No issued permit or public notice is listed.
Timeline
- Jun 5, 2026Applied Digital enters a 15-year lease for 210 MW at Delta Forge 2, with three five-year renewal options.Form 10-Q, Note 17
- Jun 8, 2026Applied Digital announces the lease, in “a new southern state.” Initial operations expected Q1 2028.Applied Digital release; Form 8-K, June 9
- Sep 24, 2026Applied Digital names Brookwood as the site: $3.2B+ investment, $270M in community benefit payments over 20 years.Applied Digital release
- Oct 1, 2026Act 2026-610 takes effect, setting PSC review of utility contracts with data centers of 150 MW or more.Alabama Legislature, SB270
- Oct 7, 2026Applied Digital lists Delta Forge 2 in Alabama as under construction; 10-Q gives delivery in the first half of 2028.Applied Digital Q1 FY2027 release; Form 10-Q
- Oct 2026PSC adopts review procedures for Alabama Power data center contracts: public petition, vote within 90 days or deemed approved.Alabama PSC order, Docket 33709
- Nov 6, 2026Tracker check: ADEM lists an air permit application for the site; no PSC petition naming the project.ADEM Tuscaloosa County page; Alabama PSC public access
- 1H 2028Target: delivery and initial operations.Applied Digital release; Form 10-Q
Figures in conflict
| Item | June 8 release | Form 10-Q | Sept. 24 release |
|---|---|---|---|
| Timing | Initial operations Q1 2028 | Delivery first half of calendar 2028 | Operations in 2028 |
| Cooling | Proprietary waterless cooling | Not stated | Closed-loop cooling |
| Lease date | Announced June 8 | Entered June 5 | “Previously announced” |
Sources
- Applied Digital, Delta Forge 2 lease release, June 8, 2026
- Applied Digital Form 8-K, June 9, 2026
- Applied Digital, “Applied Digital Announces Brookwood, Tuscaloosa County, Alabama, as Home of $3.2 Billion AI Factory Campus Investment,” Sept. 24, 2026 (TR Newswire)
- Applied Digital, fiscal first quarter 2027 results, Oct. 7, 2026
- Applied Digital Form 10-Q, quarter ended Aug. 31, 2026 (Note 17)
- Alabama Legislature, SB270 (Act 2026-610), effective Oct. 1, 2026
- Alabama PSC, order adopting procedures, Docket 33709, October 2026
- Alabama Power, large-load data center agreements
- Alabama PSC public access, recent filings, checked Nov. 6, 2026
- ADEM, Tuscaloosa County permit applications received, checked Nov. 6, 2026