Data Centers

A Maryland County Extends Data Center Pause Through Feb. ‘28 

Carroll County, Maryland, extended its pause on data center development through Feb. 19, 2028, allowing time to consider a permanent ban and assess legislation emerging from the next General Assembly session.

It’s the latest local government to take action to give themselves more breathing room and time to study the full impact should any data center decide to locate there.

“We are not simply a bypass and a byway for power lines,” county board President Joseph Vigliotti said during its session. He said the county was fighting transmission lines because data centers and AI centers in Northern Virginia require that much energy.

Carroll County is in north central Maryland, northwest of Baltimore and along the Pennsylvania border. It had an estimated 176,677 residents as of July 1, 2025, according to U.S. Census Bureau estimates published by the Maryland Department of Planning.

County commissioners voted unanimously Thursday after hearing public speakers, including  Shannon Hope and Jean Schwartz. One speaker at the meeting, Shannon Hope, supported deferral “for all the foreseeable future, if at all possible.” 

Another, Jean Schwartz, urged a ban and farmland protection. Planning staff and the Planning and Zoning Commission will consider amendments prohibiting data centers in all zoning districts.

Lawrence Berkeley National Laboratory estimates data centers could consume 11.8 percent of U.S. electricity by 2030. Its June 2026 “2025 Update” gives a range of 9.5 percent to 15.3 percent, reflecting equipment shipments, AI chip operating lifetimes, idle power and server utilization.

The February deferral was set to expire in about three months—Feb. 19, 2027. The posted draft’s operative text suspends processing, review and approval of all data centers under Section 158.176. A recital says staff and the planning commission need additional time to finalize a recommendation for a possible zoning text amendment.

The posted draft’s title and operative text set Feb. 19, 2028, as expiration. One recital calls for a “six (6) month deferral.”

Christopher Heyn, director of planning and land management for the county, said staff briefed commissioners in May and returned in October with additional information. Commissioners then directed staff to arrange the hearing and begin discussions with the planning commission about prohibiting the facilities.

Heyn said the extra year would allow the county to assess Gov. Wes Moore’s executive order, studies by larger jurisdictions, discussions with the Maryland Association of Counties and potential legislation in the next General Assembly session. He said the deferral would allow those efforts to “kind of coalesce.”

A recital in the posted draft defines “Data Center” as buildings housing computer systems, computer storage equipment and associated infrastructure used to organize, process, store and disseminate large amounts of data. It sets no power threshold. The operative text refers to Section 158.002. Heyn said he considered the existing language broad enough to cover a submitted project. Staff would return to commissioners if a gap emerged, he said.

Moore’s Sept. 23 executive order establishes the Maryland Data Center Accountability Task Force and covers facilities with peak demand of at least 25 megawatts, expansions adding that much demand or customers meeting the “Large Load Customer” definition under Public Utilities Section 7-232. 

Exclusions cover facilities owned or operated by, or principally dedicated to the research, clinical or institutional mission of, an accredited higher education institution or a health care institution, and facilities operated by or principally serving state agencies or the Defense Department. 

The chair confirms exclusions project by project upon the task force’s recommendation.

The order directs the task force to create and maintain a dashboard listing projects, developers, projected electricity demand, water use and requested state engagements’ status. State engagement includes discretionary permitting, tax credits and exemptions, site-selection assistance, letters of support and advocacy for projects before utilities, grid operator PJM Interconnection or the Federal Energy Regulatory Commission.

Moore has committed to seeking repeal of Maryland’s data center sales and use tax exemption, enacted in 2020, during the coming legislative session. His administration announced that position alongside the executive order. Repeal would require action by the General Assembly.

Lawmakers considered a broader repeal measure earlier this year. House Bill 560, sponsored by Del. Julie Palakovich Carr and other delegates, would have eliminated the sales tax exemption and local authority to reduce or eliminate assessments on qualifying data center equipment. Its recorded status remained at the House committee hearing stage.

Del. Sheila Ruth’s 2026 House Bill 1411 defined a large-scale data center as having projected aggregate monthly demand of at least 20 megawatts. It would have required operator disclosures and data center plans in jurisdictions with at least 10,000 residents, excluding Baltimore City. State assistance would depend on compliance. The bill remained at the House hearing stage.

The county’s ordinance recitals cite concerns about energy consumption, cooling water, noise from generators and cooling systems, hazardous materials, electronic waste and compatibility with rural and agricultural land uses.

Commissioner Michael Guerin supported the pause and acknowledged the tax benefits, citing Loudoun County, Virginia. He said communities were regretting their decisions and the county should prevent development in the meantime. He asked: “Is there a right way to do this?” He said developers must improve their projects.