SOAR AI signs $1.17 billion in Ohio data center orders amid financing uncertainty
The company projects $175 million to $200 million in 2027 AI infrastructure revenue. Its quarterly filing cites “substantial doubt” about its ability to continue as a going concern.
SOAR AI has signed $1.17 billion in orders for an Ohio data center project as it seeks financing to build and equip the computing infrastructure.
The North Canton, Ohio-based company reported third-quarter results Monday. It trades on NYSE American under the ticker SOAR.
“The capacity for our first deployment in Ohio is under four-year take-or-pay orders, and we expect to power on the campus in the coming weeks,” CEO Chris Ensey said. “We are building SOAR AI for customers who want dedicated AI capacity under their own control.”
SOAR’s quarterly SEC filing warns there is “substantial doubt” about its ability to continue as a going concern. None of its planned buildout financing was committed as of the filing date. Third-quarter companywide revenue was $1.3 million, up from $381,000 a year earlier.
SOAR projects $175 million to $200 million in revenue from contracted AI infrastructure orders in 2027 and approximately $294 million annually once both orders are operating.
One unnamed AI customer signed a master services agreement and two four-year take-or-pay orders. Take-or-pay arrangements generally require customers to pay for contracted capacity even if they do not use it. The orders call for approximately $133 million in prepayments; SOAR had received $39.9 million by Sept. 30.
A three-year revenue backstop of approximately $215 million provides a revenue floor for the initial deployment alongside the customer’s take-or-pay commitment, including coverage of capacity outside the customer orders. Neither the earnings release nor the quarterly filing names the backstop provider.
SOAR says its Ohio campus has 154 megawatts of available power and a development roadmap reaching 480 megawatts. It targets internal campus power-on by Dec. 31. The initial deployment calls for 4,096 AMD Instinct MI355X graphics processors.
Alignment Engine signed an Aug. 25 lease for 197,449 square feet of industrial space in Chillicothe, Ohio, for data center operations. The lease provides 25 megawatts of power initially, rising to 49 megawatts by Feb. 15, 2027, and 62 megawatts by Aug. 15, 2027.
The Chillicothe lease also requires $80 million in reservation fees for up to 400 megawatts of additional power. It had not started as of the quarterly filing. The filing does not identify the leased property as the announced Ohio campus.
At the announced Ohio campus, the data hall floor is complete, cooling equipment is on site, and GPU servers, racks and long-lead electrical equipment have been ordered. SOAR hired a construction manager in October under a cost-plus contract with guaranteed maximum prices.
SOAR completed its merger with Alignment Engine on Sept. 11 and changed its name from Volato Group on Oct. 19. It continues to develop AI-powered operational systems for aviation businesses and operate Vaunt, a private aviation membership platform. Vaunt reported $5.9 million in annual recurring revenue, compared with $1.8 million in the prior year.
The company’s infrastructure business includes data centers, high-density GPU computing, high-performance networking and related technology. Its NeuralSync AI infrastructure technology platform is covered by U.S. Patent No. 12,775,572.
SOAR reported a third-quarter net loss of $33.2 million, compared with net income of $7.1 million a year earlier. The loss included $31.2 million in noncash and merger-related items, including a $25.1 million charge for a note issued to secure waivers under its convertible note facility that the parties considered necessary for the merger, and a $4.7 million warrant fair-value loss.
Adjusted EBITDA loss narrowed to $1.6 million from $2.5 million. SOAR held $41.2 million in cash at Sept. 30, up from $4.7 million at year-end 2025, and recorded $45.7 million in deferred revenue and customer deposits.
The first customer order is scheduled to begin Dec. 31, with AMD MI355X graphics processors. The second order, using AMD MI455X graphics processors, is scheduled to begin June 30, 2027.