Data Centers
America’s largest grid operator says data centers are competing for skilled workers, as costs escalate
Data center developers and electric utilities are competing for skilled labor as a nationwide construction workforce shortage pushes up the cost of expanding the power grid, America’s largest grid operator says in a new report.
PJM Interconnection’s November staff white paper cites competition from data center construction among the causes of higher estimates for projects in the transmission owner zones of Baltimore Gas and Electric, Potomac Electric Power Co. and PECO Energy. PJM’s board approved the changes Nov. 17.
PJM manages the high-voltage grid and runs wholesale power markets across all or parts of 13 states and the District of Columbia.
The white paper states: “Competition for labor, materials, manufacturing capacity and specialized resources from rapidly expanding data center construction projects, electrification initiatives, grid modernization programs and renewable interconnections have significantly increased market demand and cost escalation across the industry.”
That language explains cost changes for projects in those utilities’ zones selected in PJM’s 2022 Window 3 competitive proposal round and for Baltimore Gas and Electric’s Marley Neck substation. The white paper separately cites higher labor rates for engineering, construction and commissioning services.
PJM’s board approved a net $3.51 billion increase for previously approved transmission projects. Projects that cite labor among several reasons for higher costs account for about $3.17 billion of that increase, based on PJM’s figures. Valley Link Transmission, the developer behind three of those projects, accounts for $2.38 billion, or roughly 68 percent of the $3.51 billion increase. Its estimates also reflect land and materials costs.
Two project groups explicitly naming data center construction account for $681.94 million of the increase, approximately 19 percent of the $3.51 billion. PJM also cited higher costs for materials and equipment and limited manufacturing capacity.
An established labor shortage
Associated Builders and Contractors estimated in January that construction would need 349,000 additional workers in 2026 to balance supply and demand. It projected a need for 456,000 in 2027. ABC said retirements account for most of the 2026 need.
ABC said approximately one-fifth of electricians are older than 55. ABC linked data center construction to rising demand for electricians skilled in precision wiring. It also cited semiconductor plants as examples of megaprojects in areas where worker shortages are more severe.
The Bureau of Labor Statistics counted approximately 821,000 electrician jobs in 2025 and projects employment growth of 9 percent through 2035, with about 72,700 openings each year. Many openings will replace people retiring or leaving the occupation.
BLS says rising electricity demand from artificial intelligence and data centers, and the grid upgrades that demand requires, will create more work for electricians. Most electricians complete four- or five-year apprenticeships.
BLS projects 10 percent employment growth for line installers and repairers through 2035 and approximately 10,900 openings annually. Apprentices typically take three or four years to reach journey level.
The cost increases in PJM’s plan
The BGE, PEPCO and PECO Window 3 projects increased from $753.49 million to $1.42 billion, a $667.49 million change. PJM attributed the revisions to more developed engineering estimates, constrained equipment supplies, higher utility labor rates, permitting and competition from data center construction and other infrastructure investment.
BGE’s portion of the Bramah–High Ridge 500-kilovolt line rose from $407.11 million to $810.14 million. PJM lists the BGE project at approximately 59 miles, alongside a separate PECO project on the same line.
Marley Neck’s 115-kilovolt substation estimate increased from $107.62 million to $122.07 million, or $14.45 million. PJM repeated its explanation about competition from data centers, electrification, grid modernization and renewable interconnections, along with higher engineering, construction and commissioning labor rates. The Window 3 estimates reflected designs and engineering at least 30 percent complete; Marley Neck’s reflected 30 percent completion, according to PJM.
Another set of BGE projects selected in the 2022 Window 1 round increased from $46.16 million to $147.24 million. The Conastone–Northwest No. 2 reconductoring component alone rose from $37.76 million to $136.2 million, approximately 260 percent.
For those Window 1 projects, PJM listed four main reasons for the increase: reactivation of work from the suspended 9A project, new constructability findings, accelerated execution to meet required service dates, and higher labor rates, which PJM linked to factors including workforce shortages and wage inflation.
What contractors are reporting
A national survey conducted in July and August by the Associated General Contractors of America and the National Center for Construction Education and Research drew 1,830 respondents who answered at least one question. AGC released the findings Sept. 3.
Twenty-eight percent of respondents had performed data center work in the preceding 12 months. Among those firms, 58 percent said data centers increased competition for skilled workers, 49 percent reported wage pressure and 37 percent identified the availability of workers or subcontractors as their biggest challenge on those projects.
Among 40 data center contractors with electrician openings, 85 percent reported trouble filling them, AGC found.
Data center construction spending rose 90 percent in the year ending in September 2026, according to AGC’s analysis of Census Bureau figures. Private electric power construction rose 14 percent; other private nonresidential categories combined fell 7.8 percent.
Construction production and nonsupervisory workers earned an average of $39.36 an hour in August, up 5 percent from a year earlier, according to AGC’s analysis of BLS data. Pay for production and nonsupervisory workers across the private sector rose 3.3 percent.
Valley Link’s cost revisions
Estimates for Valley Link Transmission’s three projects in PJM’s 2024 Window 1 round rose from $2.732 billion in 2024 dollars to $5.115 billion in 2026 dollars. Valley Link cited construction labor and outside services, right-of-way and land, and materials and equipment among the cost factors.
Valley Link moved its expected in-service date from June 1, 2029, to May 31, 2031. In its notice to PJM, the developer attributed the schedule revision to more detailed routing analysis, stakeholder and regulatory engagement, and permitting work.
Costs and customers
PJM’s November revisions bring the cumulative estimated value of Regional Transmission Expansion Plan projects approved since 2000 to approximately $73.55 billion.
Under Schedule 12 of PJM’s tariff, baseline transmission costs are assigned to responsible customers, and PJM said it would file the approved cost allocations with the Federal Energy Regulatory Commission within 30 days. For generation interconnection projects, network upgrade costs are the responsibility of the project developer.
PJM says cost-containment provisions for most BGE and PEPCO Window 3 projects are intended to soften the effect of the increases on rates. The applicable provisions are detailed in the projects’ Designated Entity Agreements.