Buildout Tracker
GW Ranch
Buildout Tracker (beta): Pacifico Energy holds a TCEQ air permit for up to 7.65 GW of off-grid gas generation north of Fort Stockton, and Amazon Data Services registered a $300 million first data center building on the same highway for an August 2026 start; no county incentive is on record and neither company names the other.
GW Ranch
Pacifico GW LLC applied to the Texas Commission on Environmental Quality on Aug. 4, 2025 for a new natural gas-fired power plant on Highway 18 about 17 miles north of Fort Stockton, the GW Ranch Energy Center, that the agency’s notice says will power an on-site data center campus and will not connect to or sell power to the grid. TCEQ issued its preliminary decision Dec. 4, 2025 under an expedited review, with proposed annual emissions of 2,830 tons of nitrogen oxides, 5,955 tons of carbon monoxide, 999 tons of particulate matter and 33.2 million tons of carbon dioxide equivalent, controlled by selective catalytic reduction and oxidation catalysts. Pacifico Energy announced the permit on Jan. 26, 2026 as authority for 7.65 GW of gas generation alongside 1.8 GW of battery storage and 750 MWac of solar on more than 8,000 acres, with turbines secured, a 1 GW first phase delivering power in the first half of 2027, more than 5 GW by 2031, and a 15-mile, 1 billion cubic feet a day pipeline to the Waha hub, all on a private grid the company says will not touch Texas ratepayers.
Amazon put its name on the site in August. Amazon Data Services, Inc. registered a “Pecos County Data Center” with the Texas Department of Licensing and Regulation on Aug. 4, 2026 at 6000 TX-18, Fort Stockton: new construction, 189,060 square feet, an estimated $300 million, designed by Gensler, with a start date of Aug. 1 and a listed completion of Dec. 1, 2026. Six days later Amazon said its planned Pecos County campus would run on new on-site generation, move to grid-connected service “as interconnection timelines allow,” use water unsuitable for drinking or irrigation and explore produced water, and create thousands of jobs, without naming its power supplier. Pecos County’s commissioners court agendas from July through Nov. 23 carry no abatement, reinvestment zone or Chapter 381 item for Amazon or Pacifico; the Nov. 23 agenda does include tax abatements for Greasewood III, LLC and Marigold BESS, LLC, a retainer for counsel on a tax increment reinvestment zone and other economic development projects, and donations from Poolside AI of $1.42 million for county emergency radios and $220,250 for a fire pumper. Gov. Abbott’s Aug. 3 freeze reaches data centers in ERCOT’s interconnection process, which this off-grid campus is not, and his Sept. 21 TCEQ permit halt came eight months after GW Ranch’s permit.
Project status
Tracker update: Nov. 21, 2026Status board
Pacifico cites $5 billion-plus raised company-wide and turbines secured; no project financing, offtake or EPC disclosed. Amazon’s TDLR registration values the first building at $300 million.
TCEQ 181033 / PSDTX1672 / GHGPSDTX255: application Aug. 4, 2025; preliminary decision Dec. 4, 2025; issuance announced Jan. 26, 2026 (final TCEQ document not retrieved). No ERCOT or PUCT record. TDLR building registration Aug. 4, 2026. No county incentive on 2026 agendas reviewed.
Pacifico: construction start Q1 2026, first power H1 2027, 1 GW in 2028, 5 GW-plus by 2031. Amazon building: start Aug. 1, 2026 per TDLR.
Stage gauge
- 1Air permit applicationAug. 4, 2025
- 2TCEQ preliminary decisionDec. 4, 2025
- 3Permit announcedJan. 26, 2026, 7.65 GW
- 4Amazon registrationTDLR, Aug. 4, 2026
- 5First building189,060 sq ft; start Aug. 1, 2026
- 6Phase 1 power1 GW, H1 2027 target
- 7Grid connection“As interconnection timelines allow”
- 85 GW-plus2031 target
By the numbers
The energy center is a greenfield site on Highway 18 about 17 miles north of Fort Stockton; Amazon’s registered address is 6000 TX-18. Pacifico describes more than 8,000 build-ready acres with room for expansion, a mix of small and large gas turbines with selective catalytic reduction and oxidation catalysts, carbon-capture-ready controls, N+2 redundancy and 99.99 percent availability, self-supplied water with no major external source, and gas from multiple laterals including a dedicated 15-mile, 1 Bcf/d line to Waha. TCEQ’s preliminary decision shows the plant consuming 6.2 of 9 micrograms per cubic meter of the 24-hour PM2.5 PSD increment. Amazon says it will use water unsuitable for drinking or irrigation, custom cooling and possibly produced water, and is exploring on-site solar and storage.
Timeline
- Aug. 4, 2025Pacifico GW LLC submits the air permit application for the GW Ranch Energy Center.TCEQ NAPD
- Dec. 4, 2025TCEQ issues the Notice of Application and Preliminary Decision under expedited review; 30-day comment and hearing-request window.TCEQ NAPD
- Jan. 26, 2026Pacifico announces the 7.65 GW permit, 1.8 GW BESS, 750 MWac solar, turbines secured, first power H1 2027.Pacifico release
- Aug. 3, 2026Gov. Abbott orders an audit of data centers in ERCOT’s interconnection process.Governor’s Office
- Aug. 4, 2026Amazon Data Services registers the Pecos County Data Center with TDLR: $300 million, 189,060 sq ft, start Aug. 1.TDLR TABS2026026955
- Aug. 10, 2026Amazon statement: on-site generation, grid service as interconnection allows, non-potable water, thousands of jobs.Amazon
- Sept. 21, 2026Governor directs TCEQ to halt data center permits pending the ERCOT audit.Governor’s Office
- Nov. 23, 2026Pecos County agenda: abatements for Greasewood III and Marigold BESS, TIRZ counsel, Poolside AI donations; no Amazon or Pacifico item.Commissioners court agenda
- Dec. 1, 2026Listed completion date for the first Amazon building.TDLR
- H1 2027Phase 1, 1 GW gross, first power.Pacifico
- 2031More than 5 GW of capacity online.Pacifico
Sources
- TCEQ — Notice of Application and Preliminary Decision, Pacifico GW LLC, Permit 181033/PSDTX1672/GHGPSDTX255 (Dec. 4, 2025)
- TCEQ — Plain Language Summary, GW Ranch Energy Center
- Pacifico Energy — release, 7.65 GW permit (Jan. 26, 2026)
- Pacifico Energy — GW Ranch project page
- Amazon — statement on a planned data center campus in Pecos County (Aug. 10, 2026)
- Texas Department of Licensing and Regulation — TABS2026026955, Pecos County Data Center (Aug. 4, 2026)
- Pecos County Commissioners Court — agenda, Nov. 23, 2026
- Office of the Texas Governor — data center audit directive (Aug. 3, 2026)
- Office of the Texas Governor — TCEQ permit halt (Sept. 21, 2026)