How Will We Know If an AI/Data Center Bubble Is Bursting?
- Past bubbles gave off warning signs before they burst. In the housing crash, the first ones showed up in lending. In the dot-com crash, they showed up in overbuilding and in companies lending money to their own customers.
- You can track most of those signs yourself, for free, in company reports, government data and your own town’s planning agendas.
- As of October 2026, the borrowing and lending signs show stress, while demand for data center space remains strong.
The race to build artificial intelligence is among the largest technology-driven investment booms in U.S. history, according to the Bank for International Settlements, which is owned by 60 central banks and monetary authorities. Amazon, Microsoft, Alphabet and Meta have told investors they expect to spend roughly $700 billion combined on buildings and equipment in 2026. Much of it goes into data centers.
Before the dot-com and housing crashes, warning signs appeared before prices fell. The same kinds of signs can be tracked today, most of them for free.
What a bubble is
A bubble is when the price of something, or the amount of money going into it, grows far faster than what it will earn. It ends when buyers and lenders decide the earnings are coming too slowly and pull back.
For AI, the test is whether the money being spent now can be paid back on the schedule investors and lenders expect.
What the last two busts showed
The dot-com and telecom crash, 2000 to 2002
The Nasdaq stock index peaked on March 10, 2000, and fell 78 percent by October 2002. Three things stood out beforehand.
First, companies built far more than anyone was using. Telecom carriers buried fiber-optic cable across the country. In 2002, a report from the Federal Deposit Insurance Corp. cited estimates that only about 2 percent to 5 percent of installed fiber was lit, meaning actually carrying traffic.
Second, equipment makers lent money to their own customers so those customers could keep buying. Lucent’s financing commitments to its customers reached $8.1 billion in September 2000. A year later, customers had drawn $3.0 billion of that money, and Lucent had set aside $2.1 billion to cover expected losses on it.
Third, a large volume of stock came onto the market. Newly public companies usually bar insiders from selling their shares for 180 days. Economists Eli Ofek and Matthew Richardson tied the internet-stock collapse to an unprecedented wave of those waiting periods ending at once, and the insider selling that followed.
The housing crash, 2006 to 2009
From 2002 to 2005, mortgage lending grew fastest in neighborhoods where income growth was falling behind, according to research by economists Atif Mian and Amir Sufi. Loans were growing faster than people’s ability to repay them.
The first signs of trouble came in lending markets. Prices on bonds made of subprime mortgages started showing stress in the fall of 2006, months before most of the public heard about it. Home prices nationally peaked in mid-2006 and fell roughly 27 percent to 35 percent by 2012, depending on which index you use.
Borrowed money does the most damage
A study of 140 years of bubbles in 17 countries, by economists Òscar Jordà, Moritz Schularick and Alan Taylor, found that bubbles built on borrowed money were followed by deeper recessions and slower recoveries. The dot-com bubble was mostly stock money; the recession that followed lasted eight months. The housing bubble was mostly loans; that recession lasted 18 months.
The signs below start with borrowing. Through 2025, the biggest tech companies could pay for their building out of cash from their own operations. In the first three months of 2025, for example, Microsoft took in $37 billion from operations and spent $17 billion on buildings and equipment. More of the building now runs on borrowed money. Alphabet alone sold more than $85 billion in bonds over the year and a half that ended in June 2026.
Nine signs you can watch yourself
Each sign below lists what to watch and what it showed as of early October 2026. Most can be checked without paid financial data.
1. Are lenders pulling back?
What to watch: News that a credit-rating firm has cut a company’s rating, that a lender has refused to fund a data center project, or that a company’s long-term bonds are selling well below face value.
Where it stands: In July, S&P Global Ratings cut Oracle, which is borrowing heavily to build data centers, many of them for OpenAI, to BBB-, one step above junk. In late September, Oracle’s bonds due in 2055 traded at 77 cents on the dollar, according to PitchBook data reported by Axios.
2. Are tenants trying to back out?
What to watch: A company that signed up to lease a data center asking to delay or cancel. These requests show up in company filings and, often first, in local news and town planning-board minutes.
Where it stands: In September, Oracle sent a force majeure notice to the developer of Project Jupiter, a data center campus in New Mexico where Oracle is the main tenant. Force majeure is a contract clause that can excuse a party when events outside its control interfere. An analyst at William Blair read the notice as preparing Oracle to defer lease payments if the campus misses its planned 2028 start. Oracle says the project remains on its planned schedule.
Residents can watch this sign directly. A data center proposal that stalls, changes developers or asks for extensions is a question to raise at the next public meeting.
3. Are chipmakers financing their own customers?
What to watch: Two numbers in a chipmaker’s quarterly report: how much it has invested in other companies, and how much its customers owe it. When both climb faster than sales, the chipmaker is helping pay for its own orders, as Lucent did.
Where it stands: Nvidia’s stakes in other companies grew from about $35 billion in January 2026 to about $94 billion by late July. Over the three months that ended in July, the average time its customers took to pay rose from about 45 days to about 60. Nvidia has also guaranteed land, power and building leases for some of the cloud companies that buy its chips.
4. Are investors pulling their money out?
What to watch: Private credit funds lend to companies, including data center builders, and many are sold to individual investors who can ask for their money back each quarter. When many ask at once, the funds limit withdrawals.
Where it stands: Withdrawal requests at 16 such funds tracked by Fitch Ratings averaged 10.3 percent of shares in the second quarter of 2026, up from 9.7 percent in the first. The funds generally cap withdrawals at 5 percent a quarter, so many investors who asked could not get all of their money out.
5. Is AI money coming in as fast as it goes out?
What to watch: The tech giants’ quarterly earnings. Two lines matter: their spending plans for the year, and free cash flow, the cash left after paying the bills and buying equipment. A cut to spending plans would mark a pullback.
Where it stands: Spending plans were still rising through the summer; Alphabet raised its 2026 plan again in July, to $195 billion to $205 billion. Free cash flow fell 22 percent at Microsoft and 47 percent at Alphabet in the first three months of 2026 compared with a year earlier. OpenAI, the maker of ChatGPT, expects to spend about $278 billion more than it takes in from 2026 through 2030, according to investor documents reported by the Financial Times.
6. Is anyone using the buildings?
What to watch: Data center vacancy rates and the rental price of AI chips. Rising empty space or falling rental prices would mean supply is running ahead of use, as it did with telecom fiber. The real estate firm CBRE publishes a free data center report twice a year.
Where it stands: Demand remains strong. Vacancy in the largest North American data center markets hit a record low of 1.4 percent in the first half of 2026, and more than 80 percent of space under construction was already leased before completion. One-year rental contracts for Nvidia’s H100 chip rose about 40 percent between October 2025 and March 2026, according to the research firm SemiAnalysis.
7. Are power companies scaling back?
What to watch: Utilities and grid operators publish forecasts of how much electricity data centers will need. A cut means fewer data centers are expected to connect.
Where it stands: On July 30, 2026, utility owner Exelon cut its high-probability data center demand from about 18 gigawatts at the end of 2025 to 11 after requiring developers to sign agreements and post collateral. On August 3, Texas Gov. Greg Abbott ordered an audit of every data center seeking to connect to the state’s main grid, where connection requests total more than 474 gigawatts, about 90% of them from data centers.
8. Are stock prices at 1999 levels?
What to watch: The cyclically adjusted price-to-earnings ratio, a measure popularized by Yale economist Robert Shiller that compares stock prices with ten years of company earnings. Also watch for large new stock sales and insiders selling shares.
Where it stands: The ratio for the S&P 500 stood at about 42 in early October 2026, its highest since 2000; it peaked at 44.19 in December 1999. Over the two years to October 9, 2026, the PHLX Semiconductor Index rose about 136%, against about 35 percent for the S&P 500. In June, Alphabet raised $50 billion by selling stock and preferred shares and set up a program to sell up to $40 billion more, partly to pay for AI construction.
9. How much of the economy depends on it?
What to watch: The quarterly GDP report from the U.S. Bureau of Economic Analysis, specifically business spending on computers and software.
Where it stands: Economists at ING estimated that AI-related investment accounted for between one-third and one-half of U.S. economic growth in the second quarter of 2026.
The bottom line
In the housing bust, the first signs appeared in lending markets months before the headlines. In the dot-com bust, they appeared in unused capacity and in equipment makers financing their customers. Today, the lending signs and the customer-financing signs show stress. Demand for the buildings remains strong. The pattern resembles late 2006 more than 2000: stress shows in lending and at the most heavily borrowed companies, while data center space is in short supply. By 2002, most of the telecom fiber sat unused. Watch the lenders, the tenants and the spending plans.
Figures in this explainer are as of October 9, 2026.