Buildout Tracker (beta): Coweta County commissioners voted 3-2 on Oct. 20 to return CyrusOne's 700 MW Project Peach site near Palmetto, Georgia, to rural conservation zoning after the developer missed deadlines for a permanent power agreement and a land disturbance permit.

Buildout TrackerBeta

CyrusOne Project Peach

Developer CyrusOne (C1 Atlanta 1 LLC; rezoning applicant of record: North Coweta Investors, LLC) Utility Georgia Power (permanent service, no contract provided); an electric membership corporation (temporary construction power) Location SR 14/U.S. 29, Weldon Road and Johnston Circle, unincorporated Coweta County, adjoining Palmetto Power About 700 MW, per the applicant’s representative Stated investment $1 billion construction value, excluding servers (applicant, 2025); $60 million spent on land, per CyrusOne Status Zoning reverted to rural conservation, 3-2, Oct. 20, 2026

Coweta County commissioners voted 3-2 on Oct. 20 to return the 323.9-acre Project Peach site to rural conservation zoning, removing the light industrial designation that allowed CyrusOne’s planned data center campus. Commissioner Bob Blackburn, who voted for the rezoning in April 2025, made the motion. Commissioner Alphonso Smith seconded, and Commissioner Bill McKenzie joined them. Commissioners John Reidelbach and Jeff Fisher voted no. The board acted under conditions attached to the 2025 approval, which required a power purchase agreement from an electric provider, a deadline the board had already extended 12 months, and a land disturbance permit by Oct. 16, 2026. Zoning staff told the board CyrusOne provided an executed agreement for temporary construction power on Oct. 16 and that site development plans entered initial review Oct. 8. No land disturbance permit had been issued, and the permanent power agreement was still outstanding. The board’s two recorded motions on the item were to close the hearing and to revert the zoning; a draft development agreement in the packet, which would have dropped the power contract requirement and moved the permit deadline to Oct. 31, 2027, was not voted on.

CyrusOne representative Brad Hout told commissioners a Georgia Power request for land along a transmission corridor forced a redesign that moved planned buildings and set the schedule back a few months. He said the company had enough power for construction and a bridge to permanent service while Georgia Power studies pending projects to sort out “who’s real, who’s not.” County officials said the temporary agreement is with an electric membership corporation and that its commercial terms were redacted. Hout said CyrusOne paid $60 million for the property, spent another $2 million to $3 million with local consultants and contractors, began a U.S. Army Corps of Engineers review of minor wetland mitigation, applied for a Georgia Department of Transportation permit to widen the site driveway and filed a sewer extension request. He said the company had not sought a tax abatement. Residents asked the board to enforce the deadlines, and a resident told commissioners opponents were submitting a constitutional objection to any new zoning conditions set through a development agreement. County records do not show CyrusOne’s next step.

Project status

Tracker update: Oct. 22, 2026

Status board

FundingNot disclosed

No project financing appears in direct sources. CyrusOne told commissioners it paid $60 million for the land and spent $2 million to $3 million locally, and that it sought no tax abatement. The applicant’s 2025 figure was $1 billion in construction value, excluding servers.

Local / grid approvalsZoning reverted

Board reverted the site from LM to RC, 3-2, Oct. 20, 2026. No land disturbance permit or permanent power contract on file. Temporary construction power agreement with an EMC executed Oct. 16; site plans in initial review since Oct. 8.

Public oppositionOrganized

Palmetto’s mayor and council members opposed the 2025 rezoning and extension. The Oct. 20 packet held 60 written comments and a constitutional objection letter from the North Coweta Coalition; residents at the hearing asked the board to enforce the deadlines.

Delays / withdrawalsDeadlines missed

Power contract deadline extended once and not met. Land disturbance permit deadline passed Oct. 16, 2026. CyrusOne cited a redesign forced by a Georgia Power request for transmission corridor land. No withdrawal on record.

Stage gauge

  1. 1Regional reviewDRI #4301 findings issued Feb. 4, 2025
  2. 2County rezoningRC to LM, 3-2, April 15, 2025
  3. 3PowerTemporary EMC construction power signed Oct. 16, 2026; no permanent Georgia Power contract provided
  4. 4Site plan reviewInitial review began Oct. 8, 2026
  5. 5Zoning revertedLM to RC, 3-2, Oct. 20, 2026
  6. 6Land disturbance permitNot issued
  7. 7ConstructionNot started
  8. 8Full buildout2036 in the 2025 plan
CompleteIn progressNot started

By the numbers

3-2Oct. 20, 2026, vote to revert the site to rural conservation
700MWElectrical load stated by the applicant’s representative
$60MLand purchase, per CyrusOne
2.1M sq. ft.Eight data center buildings in the 2025 plan
323.9Acres across seven tax parcels
105,000Peak gallons of water per day in the DRI filing
Site

The campus was planned for unincorporated Coweta County at SR 14/U.S. 29 and Weldon Road, bounded by the Palmetto N Industrial Park to the southwest, the city of Palmetto to the north and large estate lots to the southeast. The 2025 plan removed part of Johnston Circle and placed a substation of about 13 acres near the road’s current entrance and the railroad track; CyrusOne said a Georgia Power request for transmission corridor land later moved planned buildings. The regional commission found the site near both the Flint and Chattahoochee watersheds, with several streams and future flooding areas.

Timeline

  1. Feb. 4, 2025Three Rivers Regional Commission issues its Report of Findings, completing the DRI #4301 review.Three Rivers RC
  2. April 14, 2025Georgia Power issues a Letter of Service for the project.CyrusOne letter to county
  3. April 15, 2025Commissioners rezone the site from RC to LM, 3-2, with 25 conditions, including a six-month deadline for a power purchase agreement.Coweta County minutes
  4. April 15, 2025Palmetto’s mayor, three council members and four residents speak against the rezoning; no resident speaks in favor.Coweta County minutes
  5. Oct. 10, 2025Georgia Power sends CyrusOne a draft Contract for Electric Service.Georgia Power letter
  6. Oct. 21, 2025Board grants a 12-month extension for the power agreement, 4-1, and schedules a reversion hearing for October 2026.Coweta County minutes
  7. Sept. 28, 2026County staff report no power purchase agreement and no land disturbance permit.Coweta County staff summary
  8. Oct. 8, 2026Site development plans enter initial county review.Coweta County hearing
  9. Oct. 16, 2026CyrusOne provides an executed temporary construction power agreement with an EMC; the land disturbance permit deadline passes with no permit issued.Coweta County hearing
  10. Oct. 20, 2026Residents at the hearing ask the board to enforce the deadlines; opponents file a constitutional objection letter.Coweta County hearing / packet
  11. Oct. 20, 2026Board reverts the site to rural conservation, 3-2. Blackburn, Smith and McKenzie vote yes; Reidelbach and Fisher vote no.Coweta County motion record

Sources

  1. Coweta County Board of Commissioners — Agenda, motion record and video, Oct. 20, 2026
  2. Coweta County — October 20 Board of Commissioners Meeting Recap (Oct. 21, 2026)
  3. Coweta County — Project Peach draft zoning conditions (Oct. 13, 2026)
  4. Coweta County — Project Peach draft development agreement with C1 Atlanta 1 LLC (Oct. 13, 2026)
  5. Coweta County Board of Commissioners — Minutes excerpt, April 15, 2025
  6. Coweta County Board of Commissioners — Minutes excerpt, Oct. 21, 2025
  7. Coweta County Community Development — Staff summary, Rezone 24-014 (Sept. 28, 2026)
  8. CyrusOne status letter and Georgia Power support letter (Oct. 16, 2025)
  9. Three Rivers Regional Commission — DRI #4301 Report of Findings (Feb. 4, 2025)
Share
Ad slot · in-article

Leave a Reply

Your email address will not be published. Required fields are marked *

B

American Buildout Podcast

Episode player

▶
--:-- / --:--
Coming soonAmerican Buildout Podcast