Homer City Energy Campus

Buildout Tracker (beta): Homer City Energy Campus, Indiana County, Pa. — a 4.5 GW gas-fired power campus under construction on the former coal plant site, with an Amazon Data Services plan for 39 data center buildings on about 2,200 acres now under a 90-day county review and the air permit under appeal.

Buildout Tracker

Homer City Energy Campus

Developer Homer City Redevelopment / Homer City Generation LP (Knighthead Capital Management); Kiewit Power Constructors, EPC Tenant Amazon Data Services, Inc. (applicant); anticipated end user AWS, per Indiana County Location Former Homer City Generating Station, Center and Blacklick townships, Indiana County; 3,200 acres Power Up to 4.4 GW on-site gas generation: seven GE Vernova 7HA.02 combined-cycle units plus up to 10 simple-cycle units permitted Stated investment More than $10 billion for power infrastructure and site readiness; data center investment not disclosed Status Power plant under construction, first power targeted for early 2028; AWS 39-building plan tabled by the county Planning Commission Nov. 18, with review running to Jan. 12, 2027; air permit under appeal

Homer City Redevelopment announced on April 2, 2025 that it would turn Pennsylvania’s largest former coal plant into a gas-fired power campus of up to 4.5 gigawatts, with Kiewit Power Constructors as engineering, procurement and construction contractor, seven GE Vernova 7HA.02 turbines, financing led by Knighthead Capital Management, more than $10 billion for initial power infrastructure and site readiness, construction starting in 2025 and first power by 2027. EQT signed a non-binding agreement in principle on July 15, 2025 to be the exclusive gas supplier, up to 665,000 MMBtu a day from the Texas Eastern and Eastern Gas Transmission systems. The Pennsylvania Department of Environmental Protection issued Air Plan Approval 32-00457A on Nov. 18, 2025, covering seven combined-cycle turbines with duct burners and up to 10 Mitsubishi FT8 simple-cycle units, with facility-wide limits of 1,142.8 tons a year of NOx and 17.55 million tons of CO2-equivalent, after 573 public comments and a Sept. 17 hearing. Clean Air Council, PennFuture and the Sierra Club appealed the approval to the Environmental Hearing Board on Dec. 17, 2025, arguing among other things that DEP failed to review the data center campus as part of the project. In its Oct. 20, 2026 update, Homer City Generation said more than 2,000 tradespeople are on site, vertical construction began in April, demolition and excavation finished in June ahead of schedule, the first two heat recovery steam generators are installed and the first gas turbine has been set on its foundation. In a Nov. 17, 2026 announcement, Homer City Generation said the first two of seven 7HA.02 turbines were delivered and set in late September, the remaining five are scheduled to arrive by rail later in 2026 and through 2027, and the first half of the heat recovery steam generators is installed. The company said the campus will produce up to 4.4 gigawatts once complete, with first power in early 2028.

The data center half of the project reached the county record on Aug. 28, 2026, when Amazon Data Services, Inc. submitted a preliminary land development plan titled “PIT100 Masterplan” to the Indiana County Planning Commission. The applicant’s narrative describes 39 data center buildings of about 225,000 square feet each on roughly 2,200 acres across six sites in Center and Blacklick townships, built in phases from December 2026 to a full build-out in mid-2036, with 1,500 to 2,000 permanent operations staff, electricity from FirstEnergy supported by the 4.5 GW plant, non-contact cooling water drawn under existing withdrawal rights and returned to the station for reuse, and AWS paying for the new electrical infrastructure. The Planning Commission accepted the plan for review on Oct. 14, setting the official filing date and a 90-day review that runs to Jan. 12, 2027, and the county commissioners the same day hired Gibson-Thomas Engineering, with subconsultants for architecture and for noise and vibration, to review the plan at the applicant’s expense. The county is separately amending its subdivision and land development ordinance for large industrial projects, having received 248 written comments by Aug. 12, and residents have spoken on the data centers at every commissioners’ meeting since: 17 on Sept. 9, three on Sept. 23 and five on Oct. 14. Gov. Josh Shapiro’s Executive Order 2026-05, signed Aug. 18, removes AI data centers from the state’s Permit Fast Track program and conditions DEP review on a binding commitment to the state’s GRID requirements and local approval.

At its Nov. 18, 2026 meeting, the Planning Commission tabled the AWS plan for further review on the recommendation of county planning staff and its SALDO committee. Josh Krug, the county’s deputy director of planning, said Navarro & Wright Consulting Engineers is advising on sound, reviewers have asked for a study of existing sound levels, and AWS has not given a clear answer on whether the project could proceed without the generators shown in the plan. Byron G. Stauffer Jr., executive director of the county planning office, said the applicant must secure required permits, including air quality permits, before final land development approval. Krug said the county commissioners hired outside legal counsel that day to assist with the review and a potential community benefits agreement, and that a developer agreement is under negotiation. Seven people spoke during public comment, four of whom urged rejection, and the county’s online portal had received 122 comments. The commission also approved a consolidation of four parcels acquired by Eagle Acquisitions at the Harvey/Gaston site; Krug said that action did not approve the AWS plan.

Project status

Tracker update: Nov. 19, 2026

Status board

FundingSponsor-financed; terms undisclosed

Knighthead Capital Management leads project financing for the power campus; no amount, lenders or closing disclosed. AWS says it will pay for the electrical infrastructure serving its campus; its investment figure is not stated.

Local / grid approvalsPlant permits issued; AWS plan tabled

DEP air plan approval (Nov. 18, 2025), Title V renewal (Feb. 26, 2026) and Chapter 102 authorizations issued; NPDES amendment and renewal pending. County accepted the AWS land development plan Oct. 14 and the Planning Commission tabled it Nov. 18; review runs to Jan. 12, 2027. The applicant must secure required permits, including air quality permits, before final land development approval, per the county planning office. No PJM or FirstEnergy interconnection filing for the data center load located.

Public oppositionPermit appealed

Environmental Hearing Board appeal of the air permit by Clean Air Council, PennFuture and Sierra Club (Dec. 17, 2025). 573 DEP comments; 25 public commenters at four county meetings since Aug. 12; seven speakers at the Nov. 18 Planning Commission meeting, four urging rejection; 122 comments on the county’s online portal; 248 written comments on the county’s SALDO amendment.

Delays / withdrawalsFirst power now early 2028

Demolition and excavation finished June 2026 ahead of schedule, per Homer City Generation. Homer City Redevelopment’s April 2, 2025 announcement stated first power by 2027; Homer City Generation’s Nov. 17, 2026 announcement states early 2028.

Stage gauge

  1. 1Announced4.5 GW campus, April 2, 2025
  2. 2Gas supplyEQT agreement in principle, July 15, 2025
  3. 3Air permitDEP Plan Approval 32-00457A, Nov. 18, 2025
  4. 4Permit appealEHB, filed Dec. 17, 2025
  5. 5Plant constructionVertical from April 2026; two of seven turbines set
  6. 6Data center planTabled Nov. 18; review to Jan. 12, 2027
  7. 7First powerEarly 2028, per Homer City Generation
  8. 8Data center build-outDec. 2026 to 2036, per applicant
CompleteIn progressNot started

By the numbers

4.4GWOn-site gas generation, per Homer City Redevelopment
$10B+Stated for power infrastructure and site readiness
39Data center buildings in the AWS plan, about 225,000 sq. ft. each, on about 2,200 acres
665,000MMBtu per day of gas supply in the EQT agreement in principle
2,000+Tradespeople on site, October 2026
573Public comments to DEP on the air permit
Site

The 3,200-acre former Homer City Generating Station sits in Center and Blacklick townships, with existing transmission ties to PJM and NYISO, substations and water access carried over from the coal plant. The DEP-permitted power block comprises seven GE 7HA.02 combined-cycle turbines rated at 3,515 MMBtu/hr each with 1,034 MMBtu/hr duct burners, ten 301 MMBtu/hr simple-cycle turbines, three auxiliary boilers and seven cooling towers; the permit requires 369 tons a year of VOC emission reduction credits before operation. The AWS plan spreads 39 buildings across six sites named Bruner, Helen, Green, West, Harvey/Gaston and Rura, phased so that Rura and West start in December 2026 and Helen finishes last in 2036. Water for the data centers would come from the plant’s existing withdrawal rights and planned treatment facilities and be returned to the station for reuse.

Timeline

  1. April 2, 2025Homer City Redevelopment and Kiewit announce the 4.5 GW gas-powered campus: seven GE Vernova 7HA.02 turbines, Knighthead-led financing, more than $10 billion, first power by 2027.Homer City Redevelopment
  2. July 15, 2025EQT agreement in principle for up to 665,000 MMBtu a day; HCR says the campus is under construction.Homer City Redevelopment
  3. Sept. 17, 2025DEP public hearing on the air plan approval at IUP; comment period closes Sept. 29 with 573 comments.DEP comment response document
  4. Nov. 18, 2025DEP issues Plan Approval 32-00457A to Homer City Generation LP; expires May 31, 2027.Pennsylvania DEP
  5. Dec. 17, 2025Clean Air Council, PennFuture and Sierra Club appeal the plan approval to the Environmental Hearing Board.Notice of appeal
  6. Feb. 26, 2026DEP issues Title V operating permit renewal 32-00055.Pennsylvania DEP
  7. April 2026Vertical construction begins with the first structure on the campus.Homer City Generation
  8. June 2026Demolition and excavation complete ahead of schedule: 112,000 tons of scrap recycled, about 3 million cubic yards moved.Homer City Generation
  9. July 11, 2026DEP posts a second draft NPDES permit amendment; renewal and Outfall 027 applications pending.Pennsylvania DEP
  10. Aug. 12, 2026County commissioners report 248 written comments on a SALDO amendment for large industrial projects including data centers; a hearing is to be scheduled.County minutes
  11. Aug. 18, 2026Gov. Shapiro signs Executive Order 2026-05 on data centers: GRID requirements, local approval, no Permit Fast Track for AI data centers.Governor’s Office
  12. Aug. 28, 2026Amazon Data Services submits the PIT100 Masterplan preliminary land development plan: 39 buildings, about 2,200 acres, 2026–2036.ICOPD / applicant narrative
  13. Sept. 9, 2026Seventeen residents address the commissioners on the proposed data centers.County minutes
  14. September 2026First heat recovery steam generators arrive on site.Homer City Generation
  15. Oct. 14, 2026Planning Commission accepts the AWS plan for review; commissioners hire Gibson-Thomas Engineering for the review, 3-0, at the applicant’s expense.ICOPD / county minutes
  16. Oct. 20, 2026Homer City Generation: 2,000+ workers, first two HRSGs installed, first gas turbine set, zero OSHA recordables.Homer City Generation
  17. Nov. 17, 2026Homer City Generation: first two of seven 7HA.02 turbines delivered and set in late September; up to 4.4 GW; first power targeted for early 2028.Homer City Generation
  18. Nov. 18, 2026Planning Commission tables the AWS plan for further review; county commissioners hire outside legal counsel; 122 comments on the county portal.Planning Commission meeting
  19. Jan. 12, 2027End of the 90-day county review period for the AWS plan.ICOPD
  20. May 31, 2027Air plan approval 32-00457A expires.Pennsylvania DEP
  21. Early 2028First power from the gas plant, per Homer City Generation.Homer City Generation

Sources

  1. Homer City Redevelopment — Homer City Redevelopment and Kiewit Announce Country’s Largest Natural Gas-Powered Data Center Campus (April 2, 2025)
  2. Homer City Redevelopment — Agreement in Principle for EQT Corporation to Supply the Campus (July 15, 2025)
  3. Homer City Generation — Kiewit One-Year Anniversary On Site (Oct. 20, 2026)
  4. Homer City Generation — Delivery of First Two GE Vernova 7HA.02 Natural Gas Turbines (Nov. 17, 2026)
  5. Pennsylvania DEP — Final Plan Approval 32-00457A, Homer City Generation LP (Nov. 18, 2025)
  6. Pennsylvania DEP — Comment Response Document, Plan Approval 32-00457A (Nov. 18, 2025)
  7. Pennsylvania DEP — Homer City Generation Site Redevelopment permit portal
  8. Clean Air Council, PennFuture and Sierra Club — Notice of Appeal to the Environmental Hearing Board, Plan Approval 32-00457A (Dec. 17, 2025)
  9. Indiana County Office of Planning & Development — Homer City Energy Campus / PIT100 Masterplan application status and Planning Commission schedule
  10. Indiana County Planning Commission — Meeting, Nov. 18, 2026
  11. Amazon Data Services, Inc. — Project Narrative: Homer City Energy Campus (submitted with the PIT100 Masterplan; hosted copy)
  12. Indiana County Commissioners — Minutes, Oct. 14, 2026
  13. Indiana County Commissioners — Minutes, Sept. 23, 2026
  14. Indiana County Commissioners — Minutes, Sept. 9, 2026
  15. Indiana County Commissioners — Minutes, Aug. 12, 2026
  16. Office of Gov. Josh Shapiro — Executive Order 2026-05 on data centers (Aug. 18, 2026)