Augusta planners vote thumbs down on proposed data center 10 miles from Masters course
A proposed data center campus about 10 miles from the home of the Masters golf tournament suffered a setback Monday when Augusta, Georgia, planning commissioners recommended denying its rezoning.
The Augusta Planning Commission voted 6-4 to recommend denial following a public hearing that lasted more than three hours. Residents and commissioners questioned the development’s impact on surrounding neighborhoods, its electricity requirements and the lack of an identified tenant.
“Because right now, there are more questions that people have than answers,” Stephanie Clarke, the commission’s vice chair, said in explaining her proposal to delay action for 60 days and give the applicants more time to work with residents.
Acting on behalf of the Nixon Trusts, 3 G Investments LLC is seeking to rezone about 383 acres at 1538 and 1550 Four H Club Road and 3806 Mike Padgett Highway. The proposed Nixon Technology Campus would sit near Augusta Regional Airport, south of Augusta National Golf Club, which first hosted the Masters in 1934.
The plans call for as many as seven data center buildings totaling up to 3 million square feet. The project presentation called for retaining 60 percent of the property as open space, including approximately 150 acres of forest, and keeping buildings at least 500 feet from neighboring residential properties.
Residents raised concerns about noise, air pollution, water consumption and property values. One speaker asked for projected noise levels at the nearest homes during normal operations and generator use, along with a process for handling noise complaints. A preliminary acoustical assessment presented at the hearing indicated that noise could be mitigated to meet city requirements. Project consultants proposed natural gas rather than diesel backup generators.
The consultants proposed closed-loop cooling. Jim Trotter, an attorney representing the applicants, said charging such a system would initially require 1 million to 2 million gallons of water.
The consultants said the project would preserve 90 percent of existing on-site wetlands. The state regional impact filing, DRI No. 4853, identifies the project as Nixon Technology Center and indicates the project would neither be in nor likely affect wetlands. Planning staff included Army Corps of Engineers wetland mitigation among its recommended conditions.
The filing puts the estimated peak connected electrical load at 600 megawatts and indicates existing transmission and distribution infrastructure is sufficient. Georgia Power had accepted a project intake form, according to the presentation.
Commissioner James O’Neal questioned what the project could mean for electricity customers after Georgia Power’s base-rate freeze, which extends through at least the end of 2028 and excludes fuel costs. Project representatives pointed to long-term electricity contracts and financial commitments designed to protect other customers.
Project consultants said the conceptual layout allowed them to conduct preliminary studies. Further analysis and electricity requirements would hinge on the tenant and final plans, they said.
Monday’s presentation projected approximately 1,000 permanent jobs. The regional impact filing lists 40 full-time employees and estimates the completed campus would have a value of $3 billion and generate approximately $38.8 million annually in local tax revenue.
“They’re not asking for any bond financing. They’re not asking for any reduced property taxes. There are no tax incentives on this project whatsoever,” Trotter said in response to questions about tax incentives.
Augusta adopted its data center ordinance Oct. 6, seven weeks before Monday’s hearing. Commissioners approved it on first reading Sept. 15, and the applicants filed their rezoning request Sept. 28. Trotter said the team applied under the new ordinance.
Asked by O’Neal whether anyone had approached planning staff about the property before the Planning Commission reviewed the ordinance, a project presenter said, “To my understanding, no.” The presenter said her first meeting with the planning director took place Sept. 23, at the pre-application meeting.
Commissioner Debra Spencer said Georgia’s governor-elect had called for a pause on data centers and asked how that would affect the project. Planning staff said a stricter state standard would require a local application process to take effect.
The League of Women Voters of the Central Savannah River Area challenged the legal basis for the rezoning, arguing that the city’s ordinance permits data center campuses only by special exception. Adleasia Cameron of Augusta Planning said the ordinance established a separate district and the city would refund the special exception fee. Later in the hearing, in response to a question from Commissioner George “Locke” McKnight, officials explained that the property’s mix of existing zoning classifications made it ineligible for the heavy-industrial special exception.
Planning staff recommended approval with conditions. After a motion to recommend approval, Clarke offered a substitute motion to defer action. A city attorney questioned whether the Planning Commission had authority to defer the matter on its own. Clarke amended her motion to recommend a deferral, but it failed to receive a second. McKnight then moved to recommend denial, and the motion passed.
The Augusta Commission, which has final authority over rezoning, is scheduled to hear the petition at 2 p.m. Dec. 1.