Buildout Tracker

Project Ruby

Buildout Tracker (beta): Habitat Partners’ $5.18 billion Project Ruby data center campus in Upatoi, Muscogee County, Georgia has its Technology Overlay District — adopted 6-2 by Columbus Council in June — but the site has not been rezoned, a lawsuit over the overlay’s adoption is in discovery and the Development Authority says the project is on hold.

Buildout Tracker

Project Ruby

Developer Habitat Partners, with the Development Authority of Columbus Tenant Not disclosed Location Upatoi area, northeast Muscogee County (Columbus Consolidated Government) Power Not stated in any public document; no Georgia Power filing located Stated investment More than $5.18 billion, phased 2027–2030 Status Overlay adopted 6-2; project on hold pending lawsuit; site rezoning not filed; no DRI submission on record

The Development Authority of Columbus announced on Feb. 12, 2026 that Habitat Partners plans a corporate data center campus in Columbus with more than $5.18 billion in capital investment phased from 2027 to 2030, about 195 jobs paying $80,000 to $120,000, and projected property tax revenue of $68.7 million a year by 2030. The city’s answer was a Technology Overlay District, text amendment REZN-02-26-0289, written to govern hyperscale campuses: a 75-acre minimum site under single ownership, a 75-foot height cap, a 500-foot vegetated buffer along residential lines, noise limits of 65 dBA by day and 55 dBA at night at residential boundaries with fines up to $1,000 a day, no evaporative open-loop cooling, no diesel backup generators, dark-sky lighting, and a mandatory development agreement with a developer-funded decommissioning reserve. The Planning Advisory Commission recommended it 5-1 in March with the buffer raised from 200 to 500 feet. Council took first reading June 2, amended the ordinance June 9 and adopted it June 16 by a 6-2 vote as Ordinance 26-034, with Councilors Simi Barnes and Joanne Cogle opposed and two members absent. Councilor John Anker called it a zoning tool rather than a vote on any project; Cogle called it premature and short on enforceable protections.

Columbus Water Works told Council on June 9 that the campus at full build-out would draw about 330,000 gallons a day with recirculated cooling, against current system use of 32 million gallons a day and a permitted 90 million, and that the developer would pay the roughly $30 million cost of new water mains, force mains and lift stations. The overlay attaches to land only through a parcel-by-parcel zoning change with a Planning Advisory Commission hearing and two Council readings, and the amended ordinance makes any such change a Development of Regional Impact subject to state review. No rezoning of the Upatoi parcels has appeared on a Council agenda through Oct. 27. The Development Authority told its board July 9 that a lawsuit had been filed over the procedure used to adopt the overlay and that the project “is on hold until the lawsuit is addressed”; on Sept. 10 it reported that a hearing was held Sept. 9 and the judge allowed a 60-day discovery period. Residents have filled the public agenda at Council meetings since March; on March 24 alone, 11 signed up to speak on the data center.

Project status

Tracker update: Oct. 27, 2026

Status board

FundingStated, not financed

Habitat Partners and the Development Authority state more than $5.18 billion over 2027–2030. No financing, tenant or lease has been disclosed. The developer bears about $30 million in water and sewer extensions, per Columbus Water Works.

Local / grid approvalsOverlay adopted; site not rezoned

Technology Overlay District adopted June 16, 2026 (Ordinance 26-034, 6-2). The site still needs a parcel-specific zoning change to the overlay, a development agreement and a state DRI review; the state DRI database shows no Muscogee County submission in 2025 or 2026. No Georgia Power filing located.

Public oppositionIn court

A lawsuit challenges the procedure used to adopt the overlay; hearing Sept. 9, 2026, with a 60-day discovery period. Residents have spoken against the project at nearly every Council meeting since March.

Delays / withdrawalsOn hold

The Development Authority told its board July 9 that the project is on hold until the lawsuit is addressed.

Stage gauge

  1. 1AnnouncedDevelopment Authority, Feb. 12, 2026
  2. 2Overlay recommendedPAC 5-1, March 4 and 18, 2026
  3. 3Utility capacityColumbus Water Works, June 9, 2026
  4. 4Overlay adoptedOrdinance 26-034, 6-2, June 16, 2026
  5. 5LitigationHearing Sept. 9; 60-day discovery
  6. 6Site rezoning to overlayNot filed
  7. 7DRI review and development agreementNot started
  8. 8ConstructionInvestment phased 2027–2030, per developer
CompleteIn progressNot started

By the numbers

$5.18BStated capital investment, 2027–2030
75Minimum acres for any overlay site, in one tract under common ownership
195Jobs at $80,000–$120,000, per the Development Authority
$68.7MProjected annual tax revenue by 2030, before depreciation
330,000Gallons per day at full build-out, per Columbus Water Works
6–2Council vote adopting the Technology Overlay District
Site

The campus is planned in the Upatoi area of northeast Muscogee County, inside the consolidated city-county government of Columbus. Under Ordinance 26-034 any overlay site must be at least 75 acres in one contiguous tract under common ownership, keep buildings under 75 feet, hold a 500-foot vegetated buffer from residential property lines, meet 65/55 dBA day/night noise limits at residential boundaries, use closed-loop, direct-to-chip or immersion cooling without PFAS or hydrofluorocarbon fluids, forgo diesel backup generators, and fund a decommissioning reserve held by the city. Columbus Water Works would serve it through new 8-inch water mains and about 45,000 feet of sewer force main with two new pump stations, and says the campus would rank fifth among its largest customers.

Timeline

  1. Feb. 12, 2026Development Authority of Columbus announces Habitat Partners’ data center campus: more than $5.18 billion, about 195 jobs, $68.7 million a year in projected tax revenue by 2030.Development Authority of Columbus
  2. March 4 and 18, 2026Planning Advisory Commission recommends the Technology Overlay District 5-1, conditioned on raising the residential buffer from 200 to 500 feet.Council staff report
  3. March 24, 2026Eleven residents sign up to address Project Ruby and data centers (eight speak); a “Moratorium on Project Ruby” document is distributed to Council.Council minutes
  4. June 2, 2026First reading of REZN-02-26-0289, continued as amended by substitute.Council agenda
  5. June 9, 2026Ordinance amended on first reading. Columbus Water Works presents: 330,000 gallons a day at build-out, about $30 million in developer-paid extensions, sufficient capacity.Council agenda / CWW presentation
  6. June 16, 2026Council adopts the Technology Overlay District as Ordinance 26-034, 6-2 (Barnes, Cogle no; Huff, Tucker absent).Council minutes
  7. By July 9, 2026Lawsuit filed against the city over the procedure used to adopt the overlay; the Development Authority says the project is on hold until it is addressed.Development Authority minutes
  8. Sept. 9, 2026Hearing held on the overlay lawsuit; the judge allows a 60-day discovery period.Development Authority minutes, Sept. 10
  9. Oct. 13 and 27, 2026Council agendas carry no Project Ruby rezoning item; the Sept. 10 Development Authority minutes are received Oct. 27.Council agendas
  10. Early Nov. 2026Sixty-day discovery period from the Sept. 9 hearing runs out.Development Authority minutes
  11. 2027–2030Investment phasing stated by the developer; no construction schedule published.Development Authority of Columbus

Sources

  1. Development Authority of Columbus — Columbus, Georgia Set to Benefit from Major New Technology Center Campus (Feb. 12, 2026)
  2. Columbus Council — Minutes, June 16, 2026 (Ordinance 26-034, REZN-02-26-0289)
  3. Columbus Council — Technology Overlay District ordinance as amended June 9, 2026 (second reading June 16)
  4. Columbus Planning Department — Council Staff Report, REZN-02-26-0289
  5. Columbus Water Works — Presentation to Council on Project Ruby water and sewer service (June 9, 2026)
  6. Columbus Council — Agenda, June 9, 2026
  7. Columbus Council — Minutes, March 24, 2026
  8. Development Authority of Columbus — Minutes, July 9, 2026
  9. Development Authority of Columbus — Minutes, Sept. 10, 2026
  10. Columbus Council — Agenda, Oct. 27, 2026
  11. Columbus Council — Agenda, Oct. 13, 2026