Buildout Tracker
Project Jupiter
Buildout Tracker (beta): Project Jupiter, the Oracle-anchored data center campus in Santa Teresa, New Mexico, is under construction while its fuel-cell microgrid awaits a state air permit and its gas supply awaits a federal pipeline decision.
Project Jupiter
Project Jupiter is a data center campus in Santa Teresa, in Doña Ana County, New Mexico, led by STACK Infrastructure in partnership with BorderPlex Digital Assets. Oracle is the campus tenant and will deploy AI infrastructure there for OpenAI, which named the county one of five new Stargate sites on Sept. 23, 2025. Doña Ana County puts total investment at up to $165 billion over 30 years, with a minimum initial investment of $50 billion, and adopted Industrial Revenue Bond Ordinance No. 367-2025 for the project. Phase 1 covers 400 acres, with completion anticipated in the third quarter of 2028. In April 2026, Oracle said Bloom Energy fuel cells, up to 2.45 gigawatts of installed capacity, will power the campus through an onsite microgrid in place of the gas turbines and diesel generators planned earlier.
The microgrid still needs a state air permit, and its gas supply needs federal approval. The New Mexico Supreme Court stayed the New Mexico Environment Department’s air permit proceeding in August and lifted the stay on Sept. 17; the department filed the administrative record on Oct. 9, and filings in the docket cite a Nov. 23 decision deadline. Gas would arrive through the proposed 17.8-mile Green Chile pipeline, for which the Federal Energy Regulatory Commission set a Dec. 3 deadline for federal authorization decisions. On Oct. 5, the New Mexico Department of Justice and Attorney General Raúl Torrez filed comments with FERC on the pipeline’s environmental assessment. Oracle says the data center buildings need no air permit and that all construction to date has been on the data center campus, where nearly 1,000 New Mexico residents were working as of Sept. 8. After floodwater reached the campus, Oracle and STACK said on Sept. 30 that no critical infrastructure was damaged and the project remains on its planned schedule.
Project status
Tracker update: Oct. 11, 2026Status board
County lists up to $165B over 30 years ($50B minimum initial); IRB Series 2025A–C executed and recorded.
County IRB ordinance adopted in 2025; the microgrid air permit (NMED) and Green Chile pipeline (FERC) await decisions.
Parties contested the air permit at NMED and the state Supreme Court; NM DOJ filed comments on FERC’s pipeline review Oct. 5.
No delay announced by the developers; Oracle and STACK said Sept. 30 the project remains on its planned schedule.
Stage gauge
- 1AnnouncedSTACK / BorderPlex, Sept. 2025
- 2SiteSanta Teresa, 400-acre Phase 1
- 3County approvalIRB Ord. 367-2025
- 4Power planBloom fuel cells, Apr. 2026
- 5Air permitNMED; Nov. 23 deadline
- 6Gas pipelineFERC; Dec. 3 deadline
- 7Construction~1,000 NM residents onsite
- 8OperationalPhase 1 target Q3 2028
By the numbers
Phase 1 covers 400 acres in Santa Teresa, Doña Ana County. The fuel-cell microgrid is on an adjacent site; Yucca Growth Infrastructure, an Oracle subsidiary, is the air permit applicant. Gas would arrive through the proposed 24-inch Green Chile pipeline.
Timeline
- Sept. 15, 2025STACK and BorderPlex announce $56.9M in water and community commitments and up to $165B in private investment. STACK Infrastructure
- Sept. 23, 2025OpenAI names Doña Ana County one of five new Stargate sites, developed by Oracle. OpenAI
- 2025Doña Ana County adopts IRB Ordinance No. 367-2025; bond Series 2025A–C are executed. Doña Ana County
- Apr. 27, 2026Oracle, BorderPlex and Bloom Energy move the microgrid to up to 2.45 GW of fuel cells. Oracle
- Aug. 14, 2026County opens applications for an 11-member Community Monitoring Committee. Doña Ana County
- Sept. 17, 2026NM Supreme Court stay on the NMED air permit proceeding is lifted. NMED docket AQB 26-57(P)
- Sept. 30, 2026Floodwater reaches the campus; Oracle and STACK report no critical damage and no schedule change. Oracle / STACK
- Oct. 5, 2026NM Department of Justice files comments on FERC’s Green Chile pipeline environmental assessment. FERC eLibrary
- Oct. 9, 2026NMED files the administrative record for the air permit. NMED docket AQB 26-57(P)
- Nov. 23, 2026Air permit decision deadline cited in the NMED docket. NMED docket AQB 26-57(P)
- Dec. 3, 2026FERC deadline for federal authorization decisions on the Green Chile pipeline. Federal Register
- Q3 2028Phase 1 completion target. Doña Ana County
Sources
- Doña Ana County — Project Jupiter, economic development projects page
- Doña Ana County — Project Jupiter Industrial Revenue Bond documents
- Doña Ana County — Community Monitoring Committee interest form (Aug. 14, 2026)
- STACK Infrastructure — $56.9 million in water and community commitments (Sept. 15, 2025)
- OpenAI — Five new Stargate sites (Sept. 23, 2025)
- Oracle — Oracle advances American AI innovation in New Mexico (Jan. 23, 2026)
- Oracle — Bloom Energy fuel cells to power Project Jupiter (Apr. 27, 2026)
- Oracle — Project Jupiter to provide environmental data to the public (Sept. 8, 2026)
- Oracle — Statement on construction permitting (Sept. 14, 2026)
- Oracle — Statement on Southern New Mexico floods (Sept. 30, 2026)
- New Mexico Environment Department — Docket AQB 26-57(P), YGI Microgrid air permit
- Federal Register — FERC schedule for the Green Chile Project environmental assessment (July 29, 2026)
- FERC eLibrary — NM Department of Justice comments on the Green Chile EA, Docket CP26-80 (Oct. 5, 2026)