Buildout Tracker
Project Jupiter
Buildout Tracker (beta): Project Jupiter, the Oracle-anchored data center campus in Santa Teresa, New Mexico, is under construction while its fuel-cell microgrid awaits a state air permit and its gas supply awaits a federal pipeline decision.
Project Jupiter
Project Jupiter is a data center campus in Santa Teresa, in Doña Ana County, New Mexico, led by STACK Infrastructure in partnership with BorderPlex Digital Assets. Oracle is the campus tenant and will deploy AI infrastructure there for OpenAI, which named the county one of five new Stargate sites on Sept. 23, 2025. Doña Ana County puts total investment at up to $165 billion over 30 years, with a minimum initial investment of $50 billion, and adopted Industrial Revenue Bond Ordinance No. 367-2025 for the project. Phase 1 covers 400 acres, with completion anticipated in the third quarter of 2028. In April 2026, Oracle said Bloom Energy fuel cells, up to 2.45 gigawatts of installed capacity, will power the campus through an onsite microgrid in place of the gas turbines and diesel generators planned earlier.
The microgrid still needs a state air permit, and its gas supply needs federal approval. Yucca Growth Infrastructure, the Oracle subsidiary applying for the air permit, submitted a revised microgrid design to the New Mexico Environment Department on Oct. 16. Oracle said the revision adds an enforceable cap on fuel-cell output and cuts permitted emissions about 35 percent, with greenhouse gas emissions falling from about 8.8 million to 5.7 million tons a year. The department said in an Oct. 22 filing that the revisions require additional technical review. On Nov. 3, Yucca and the department jointly asked the hearing officer to vacate the public hearing set to begin Dec. 7 in Sunland Park, and Yucca waived the Nov. 23 decision deadline. Under the motion, no new hearing would be scheduled until the department files a revised recommendation. New Energy Economy filed a renewed motion Nov. 4 to dismiss the application without prejudice.
Gas would arrive through the proposed 17.8-mile Green Chile pipeline, for which the Federal Energy Regulatory Commission set a Dec. 3 deadline for federal authorization decisions. The New Mexico Department of Justice filed comments with FERC on the pipeline’s environmental assessment Oct. 5, and a coalition of 12 state attorneys general led by West Virginia filed comments Oct. 15 urging approval. On Oct. 13, Oracle proposed an energy service agreement with El Paso Electric to power late-stage construction, commissioning and emergency backup at the campus, and said the Bloom fuel-cell microgrid remains the primary power source. Oracle says the data center buildings need no air permit and that all construction to date has been on the data center campus, where nearly 1,000 New Mexico residents were working as of Sept. 8. After floodwater reached the campus, Oracle and STACK said on Sept. 30 that no critical infrastructure was damaged and the project remains on its planned schedule.
Project status
Tracker update: Nov. 6, 2026Status board
County lists up to $165B over 30 years ($50B minimum initial); IRB Series 2025A–C executed and recorded.
County IRB ordinance adopted in 2025. YGI and NMED moved Nov. 3 to vacate the Dec. 7 air permit hearing, and YGI waived the Nov. 23 decision deadline; the Green Chile pipeline awaits FERC.
New Energy Economy and other intervenors seek dismissal of the air permit application, renewed Nov. 4; NM DOJ filed comments on FERC’s pipeline review Oct. 5.
YGI and NMED moved Nov. 3 to vacate the Dec. 7 air permit hearing; no new date is set. Doña Ana County lists a Q3 2028 Phase 1 completion target.
Stage gauge
- 1AnnouncedSTACK / BorderPlex, Sept. 2025
- 2SiteSanta Teresa, 400-acre Phase 1
- 3County approvalIRB Ord. 367-2025
- 4Power planBloom fuel cells, Apr. 2026
- 5Air permitNMED; deadline waived Nov. 3
- 6Gas pipelineFERC; Dec. 3 deadline
- 7Construction~1,000 NM residents onsite
- 8OperationalPhase 1 target Q3 2028
By the numbers
Phase 1 covers 400 acres in Santa Teresa, Doña Ana County. The fuel-cell microgrid is on an adjacent site; Yucca Growth Infrastructure, an Oracle subsidiary, is the air permit applicant. Gas would arrive through the proposed 24-inch Green Chile pipeline. YGI’s Oct. 16 revised design uses three tiers of fuel cells and 1,263 exhaust stacks, down from 2,275, according to NMED.
Timeline
- Sept. 15, 2025STACK and BorderPlex announce $56.9M in water and community commitments and up to $165B in private investment. STACK Infrastructure
- Sept. 23, 2025OpenAI names Doña Ana County one of five new Stargate sites, developed by Oracle. OpenAI
- 2025Doña Ana County adopts IRB Ordinance No. 367-2025; bond Series 2025A–C are executed. Doña Ana County
- Apr. 27, 2026Oracle, BorderPlex and Bloom Energy move the microgrid to up to 2.45 GW of fuel cells. Oracle
- Aug. 14, 2026County opens applications for an 11-member Community Monitoring Committee. Doña Ana County
- Sept. 17, 2026NM Supreme Court stay on the NMED air permit proceeding is lifted. NMED docket AQB 26-57(P)
- Sept. 30, 2026Floodwater reaches the campus; Oracle and STACK report no critical damage and no schedule change. Oracle / STACK
- Oct. 5, 2026NM Department of Justice files comments on FERC’s Green Chile pipeline environmental assessment. FERC eLibrary
- Oct. 9, 2026NMED files the administrative record for the air permit. NMED docket AQB 26-57(P)
- Oct. 13, 2026Oracle proposes an energy service agreement with El Paso Electric for construction, commissioning and backup power; the Bloom microgrid remains the primary source. Oracle
- Oct. 15, 2026Oracle and YGI propose a cap on fuel-cell output that cuts permitted emissions about 35 percent. Oracle
- Oct. 15, 2026A 12-state coalition of attorneys general files comments urging FERC to approve the Green Chile pipeline. West Virginia Attorney General
- Oct. 16, 2026Hearing Officer James O. Browning sets the air permit hearing for Dec. 7 in Sunland Park; YGI submits a revised application and modeling. NMED docket AQB 26-57(P)
- Nov. 3, 2026YGI and NMED jointly move to vacate the Dec. 7 hearing; YGI waives the Nov. 23 decision deadline. NMED docket AQB 26-57(P)
- Nov. 4, 2026New Energy Economy renews its motion to dismiss the air permit application without prejudice. NMED docket AQB 26-57(P)
- Nov. 23, 2026Original air permit decision deadline, waived by YGI on Nov. 3. NMED docket AQB 26-57(P)
- Dec. 3, 2026FERC deadline for federal authorization decisions on the Green Chile pipeline. Federal Register
- Q3 2028Phase 1 completion target. Doña Ana County
Sources
- Doña Ana County — Project Jupiter, economic development projects page
- Doña Ana County — Project Jupiter Industrial Revenue Bond documents
- Doña Ana County — Community Monitoring Committee interest form (Aug. 14, 2026)
- STACK Infrastructure — $56.9 million in water and community commitments (Sept. 15, 2025)
- OpenAI — Five new Stargate sites (Sept. 23, 2025)
- Oracle — Oracle advances American AI innovation in New Mexico (Jan. 23, 2026)
- Oracle — Bloom Energy fuel cells to power Project Jupiter (Apr. 27, 2026)
- Oracle — Project Jupiter to provide environmental data to the public (Sept. 8, 2026)
- Oracle — Statement on construction permitting (Sept. 14, 2026)
- Oracle — Statement on Southern New Mexico floods (Sept. 30, 2026)
- New Mexico Environment Department — Docket AQB 26-57(P), YGI Microgrid air permit
- Federal Register — FERC schedule for the Green Chile Project environmental assessment (July 29, 2026)
- FERC eLibrary — NM Department of Justice comments on the Green Chile EA, Docket CP26-80 (Oct. 5, 2026)
- NMED — Second Amended Scheduling Order, Docket AQB 26-57(P) (Oct. 16, 2026)
- NMED Air Quality Bureau — Motion for correction of the hearing record (Oct. 22, 2026)
- YGI and NMED — Joint motion to vacate the Dec. 7, 2026, hearing date (Nov. 3, 2026)
- New Energy Economy — Renewed motion to dismiss application without prejudice (Nov. 4, 2026)
- Oracle — Proposed El Paso Electric energy service agreement and customer credits (Oct. 13, 2026)
- Oracle — Project Jupiter microgrid cuts permitted emissions by 35 percent (Oct. 15, 2026)
- West Virginia Attorney General — 12-state coalition comments on the Green Chile Project (Oct. 15, 2026)