Applied Digital’s 1.2 GW North Dakota Power Deal Faces Financing Test

Applied Digital has signed a 15-year agreement to buy electricity from a proposed 1,200-megawatt natural gas plant near Center, North Dakota.
Applied Digital has signed a 15-year agreement to buy electricity from a proposed 1,200-megawatt natural gas plant near Center, North Dakota.

Applied Digital has signed a 15-year agreement to buy electricity from a proposed 1,200-megawatt natural gas plant near Center, North Dakota, tying the expansion of its Polaris Forge 3 data center campus to a power project that still has to secure financing.

The contract, disclosed in the company’s quarterly filing Wednesday, gives plant developer Base Electron the right to terminate if the project has not reached financial close by March 31, 2027.

“As new data center development becomes more difficult in certain markets, we believe the scarcity value of established, powered, and community-supported campuses increases,” Applied Digital Chief Executive Wes Cummins said in the company’s earnings release.

The company said the plant would provide dedicated generation for Polaris Forge 3. The contract calls for fixed monthly payments based on a target contract capacity, the filing says. On the company’s earnings call Wednesday, Cummins said the plant would be adjacent to the Polaris Forge 3 campus, with deliveries expected to begin in 2030.

It reported that two buildings totaling 300 megawatts of critical IT capacity are under construction at Polaris Forge 3, with initial service expected in the second half of calendar 2027 and full capacity in the second half of calendar 2028. Babcock & Wilcox, which holds the contract to design and build the plant, said in its most recent quarterly filing that the plant is targeted to begin commercial operation in 2030. Its previous quarterly filing gave a 2029 target.

The company already operates 250 megawatts at Polaris Forge 1 in Ellendale after delivering the second half of a 150-megawatt building on October 1. Its broader portfolio includes five leased U.S. campuses totaling about 1.41 gigawatts of critical IT load, according to Wednesday’s results.

Dallas-based Applied Digital develops and operates data centers for AI and other computing workloads, with five leased AI campuses and two cryptocurrency-mining facilities in the United States.

Applied Digital owns about 10 percent of Base Electron. Certain Applied Digital officers and directors, including Cummins, President Jason Zhang and director Dr. Richard Nottenburg, own and manage Base Electron in their individual capacities, along with numerous third parties, the filing says. 

Cummins is Base Electron’s chief executive, and Zhang is its president and secretary. Applied Digital’s board approved the power and credit support agreements after its Base Electron Related Party Transaction Committee reviewed and recommended them.

Applied Digital had a loan receivable from Base Electron with a principal balance of $58.5 million at Aug. 31, under a promissory note allowing advances of up to $100 million. It valued its equity stake at $2 million. The filing lists $59.3 million outstanding on the note; together with the stake, that puts Applied Digital’s maximum exposure to loss at $61.3 million. It said Applied Digital was not contractually required to provide financial support to Base Electron and provided no material noncontractual support during the quarter ended Aug. 31. On Oct. 4, after the quarter closed, Applied Digital signed a credit support agreement with Base Electron alongside the power contract.

Applied Digital treats Base Electron as a separate company in its financial statements. Its filing says Base Electron lacks enough equity at risk to finance its activities without additional subordinated support, but Applied Digital does not control the activities that most affect the developer’s results.

Babcock & Wilcox said in March that it received a full notice to proceed on a $2.4 billion design-build contract for four 300-megawatt natural gas-fired boiler and steam turbine systems. The manufacturer said the project would supply Applied Digital AI campuses. Babcock & Wilcox first signed a limited notice to proceed with Applied Digital in November 2025. Its definitive agreement with Base Electron took effect Feb. 26, 2026.

Babcock & Wilcox’s quarterly filings say $2.0 billion of the $2.4 billion is variable charges, based on reimbursable costs plus a markup, with the remainder a fixed fee.

Oliver County’s Planning and Zoning board held a preliminary public hearing on rezoning about 312 acres from agricultural to industrial use for the plant and voted unanimously to table it for further review. Residents raised concerns about outreach, water sourcing and traffic. County commissioners separately tabled a change to the county fee schedule until December, after a Base Electron representative said the county’s formula produced a conditional-use permit application fee of about $2.4 million. Oliver County’s published Oct. 6 County Commission agenda listed the rezoning and conditional-use, building and temporary-use permit applications.

The plant also needs fuel, water and an electrical path to the data center. Cummins said on the call that Base Electron’s generation will be “front of the meter, grid connected.” The filing does not disclose the contract price, the target capacity, how Base Electron will finance construction, a gas supply agreement, water rights, interconnection terms, a construction timetable or the terms of the credit support agreement.

Black Hills Corp. says Google will bear the costs of new gas generation for a planned data center in Cheyenne, Wyo. The utility signed service agreements effective Sept. 30 and plans to invest $1.8 billion from 2027 through 2029 in about 564 megawatts of generation. Google has advanced $399 million for equipment with long lead times, Black Hills said Oct. 6. Black Hills has its air quality permit; an industrial siting permit and transmission approvals are pending.

With Base Electron’s plant targeted for 2030 and Polaris Forge 3 scheduled to begin service in the second half of calendar 2027, neither the filing nor Wednesday’s earnings call addresses how the campus will be powered in the interim.

Applied Digital said Base Electron is developing generation that could add multiple gigawatts of power in the Dakotas over time.