OpenAI Project Camellia

Buildout Tracker (beta): OpenAI’s $20 billion, 3.2 GW Project Camellia in Effingham County, Georgia has a 25-year Georgia Power deal and state clearance to proceed — and now faces two lawsuits over how the zoning and a ~$900 million tax break were approved.

Buildout TrackerBeta

OpenAI Project Camellia

Developer OpenAIProject CamelliaLocation Effingham County, Ga.Capacity 3.2 GW (3,210 MW)Investment $20B (stated)Power online Phased 2028–2032

OpenAI’s Project Camellia is a planned $20 billion data center campus in Effingham County, Georgia, in the Savannah Gateway Industrial Hub near Rincon. Announced July 22, 2026, it would cover roughly 1,400 acres and about 4.4 million square feet and draw a peak electrical load of 3,210 megawatts — 3.2 gigawatts — making it the largest single electricity consumer in Georgia’s history. OpenAI signed a 25-year agreement with Georgia Power to serve the site in phases from 2028 through 2032, agreed to pay the full cost of the serving infrastructure, and agreed to let the utility curtail up to 1,000 megawatts of the facility’s demand at peak times. A state review lists the campus using about 30,000 gallons of water a day through closed-loop cooling. The project is one piece of OpenAI’s plan to spend roughly $750 billion on AI infrastructure through 2030.

The approvals are partly done and under challenge. Georgia Public Service Commission staff reviewed the Georgia Power deal and declined to object, letting it proceed without a public vote, and the Coastal Regional Commission issued a 44-page Development of Regional Impact review on September 16 that flagged wetlands, flood zones, and a state-protected plant on the site. Two lawsuits are now pending. In early September, three county residents sued to void a zoning change (Ordinance 2026-352) that made data centers a by-right industrial use, arguing a required public hearing was skipped. On September 21, the conservation group One Hundred Miles and county residents, represented by the Southern Environmental Law Center, sued the county Industrial Development Authority, alleging it hid the project behind the name “Project Gateway,” gave short meeting notice, and sold public land to an OpenAI affiliate; the suit values the tax abatement at nearly $900 million. No delays, cancellations, or scale-backs have been reported.

Project status

Tracker update: Oct. 6, 2026

Status board

FundingCommitted

OpenAI commits $20B (some reports up to $30B+); part of a ~$750B infrastructure plan through 2030.

Local / grid approvalsIn review

Georgia PSC staff declined to object; CRC issued an advisory DRI; county site-plan review still pending.

Public oppositionLitigation

Two suits — a zoning challenge and an open-government suit over the IDA’s approval and ~$900M tax break.

Delays / withdrawalsNone

No delays, cancellations, or scale-backs reported.

Stage gauge

  1. 1Announced$20B, Jul 2026
  2. 2SiteSavannah Gateway Hub
  3. 3ZoningIndustrial, by-right
  4. 4IDA dealTax abatement OK’d
  5. 5Power dealGeorgia Power, 25-yr
  6. 6State/grid reviewPSC staff OK; DRI advisory
  7. 7ConstructionNot yet begun
  8. 8Power onlinePhased 2028–2032
CompleteIn progressNot started

Electricity (gigawatts)

Peak load
3.2
Grid can
curtail
1.0
01234

Announced investment ($ billions)

OpenAI stated
20
High-end
reports
30
0102030

By the numbers

$20 BStated investment (~15 yrs)
3.2 GWPeak power (3,210 MW)
~1,400Acres (~4.4M sq ft)
~$900 MTax abatement (per lawsuit)
0.03 MGDWater use (closed-loop)
2028–2032Power phased in
Site

Savannah Gateway Industrial Hub near Rincon, Effingham County — flagged by the state DRI review for wetlands and a state-protected plant on site.

Timeline

  1. Jul 22, 2026OpenAI announces Project Camellia: a $20B, 3.2 GW campus in Effingham County, part of a ~$750B plan.OpenAI
  2. Jul 2026OpenAI signs a 25-year power agreement with Georgia Power; service phased 2028–2032.Georgia Power
  3. Aug 2026Georgia PSC staff review the service deal and decline to object; OpenAI to pay full serving-infrastructure cost and allow up to 1,000 MW curtailment.Georgia PSC
  4. Sep 2, 2026Three residents sue to void the zoning change (Ordinance 2026-352) that made data centers a by-right use.Effingham Co. Superior Court
  5. Sep 16, 2026Coastal Regional Commission releases a 44-page DRI review flagging wetlands, flood zones, and a state-protected plant on site.Coastal Regional Commission
  6. Sep 21, 2026One Hundred Miles and residents, represented by SELC, sue the county IDA over notice and a ~$900M tax break.SELC / One Hundred Miles
  7. 2028–2032Georgia Power to deliver up to 3,210 MW in phases.Georgia Power

Figures in conflict

FigureOpenAI / officialOther reportsWhat’s correct
Investment$20 billion (OpenAI)“up to $30B+” (press)$20B is OpenAI’s stated figure; $30B is an unconfirmed press high-end.
Tax breakAbatement valued at ~$900M (SELC suit)“50% tax break” (early reports)A roughly 50% abatement the suit values at nearly $900M over its life.
Water use~30,000 gal/day, closed-loop (DRI)“Millions of gallons” (opposition)The DRI lists 0.03 MGD on-site; critics point to indirect and total water.

Sources

  1. OpenAI — Project Camellia announcement (July 22, 2026)
  2. Georgia Public Service Commission / Georgia Power — service-agreement review (Aug. 2026)
  3. Coastal Regional Commission of Georgia — Project Camellia Development of Regional Impact report (Sept. 16, 2026)
  4. One Hundred Miles / Southern Environmental Law Center — lawsuit vs. Effingham County Industrial Development Authority (filed Sept. 21, 2026)
  5. Effingham County Superior Court — residents v. county, zoning challenge to Ordinance 2026-352 (filed Sept. 2026)
Share
Ad slot · in-article

Leave a Reply

Your email address will not be published. Required fields are marked *

B

American Buildout Podcast

Episode player

▶
--:-- / --:--
Coming soonAmerican Buildout Podcast