FirstEnergy Wins W.Va Gas Plant OK; Says Data Center Connections in $19B Transmission Plan

Akron, Ohio-based FirstEnergy serves more than 6 million electricity customers across Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. Its $19 billion transmission program includes connections supporting data centers and artificial intelligence growth.
Akron, Ohio-based FirstEnergy serves more than 6 million electricity customers across Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. Its $19 billion transmission program includes connections supporting data centers and artificial intelligence growth.

FirstEnergy says a West Virginia order allows its utilities to contract with new large-load customers under terms protecting other customers from subsidizing the rate base associated with serving those loads.

The provision accompanies approval for Monongahela Power and Potomac Edison to build a 1,200-megawatt gas plant at Maidsville. 

Akron, Ohio-based FirstEnergy serves more than 6 million electricity customers across Ohio, Pennsylvania, New Jersey, West Virginia, Maryland and New York. Its $19 billion transmission program includes connections supporting data centers and artificial intelligence growth.

“The companies estimate the initial surcharge will increase residential customer bills by approximately $1.18 per month, or 0.9 percent,” the West Virginia Public Service Commission said in its Nov. 17 announcement.

The commission approved the Maidsville Energy Center at the existing Fort Martin coal-fired power station in Monongalia County. In their application, the utilities projected an electricity capacity shortage from 2029 through 2045.

Transmission expansion and generation plans

The company’s $19 billion transmission allocation covers four stated purposes: replacing aging equipment, adding redundancy and grid operating flexibility, expanding the regional network through PJM Interconnection projects, and making large-load connections to support data centers and AI growth.

Transmission spending is about 35 percent above FirstEnergy’s prior five-year plan. The company expects an increase of at least 25 percent above the current $19 billion level in its February 2027 roll-forward covering 2027 through 2031.

FirstEnergy also issued an initial request for proposals for another 3 gigawatts of combined-cycle gas generation, citing strong West Virginia demand. It is examining bridge power and temporary behind-the-meter arrangements and expects to provide an update in early 2027.

The 8-K and accompanying investor presentation list data center development and co-location of generation with large loads among forward-looking risks. Those statements address potential changes in electricity demand and regulation.

Plant costs and community

The approved Maidsville gas facility is scheduled by FirstEnergy to enter service Dec. 31, 2031. The order also covers 70 megawatts of utility-scale solar at Davis, Wylie Ridge and Valley Point, with service planned between 2027 and 2030.

The PSC announcement lists $2.48 billion for the gas plant and $182 million for solar. FirstEnergy’s presentation uses rounded figures of $2.5 billion and $200 million and describes the approximately $2.7 billion combined total as a Class Level 4 cost estimate.

About $2 billion of project spending falls within FirstEnergy’s 2026-2030 capital plan, which increased from $36 billion to $38 billion following the approval.

The Census Bureau’s 2024 five-year American Community Survey estimates 3,254 residents in Maidsville’s ZIP Code Tabulation Area 26541, with a margin of error of 738, and median household income of $73,444.

Financing costs and customer bills

The order authorizes a new generation surcharge providing cash recovery of allowance for funds used during construction on construction work in progress, known as AFUDC on CWIP. Recovery continues after the projects enter service until the financing costs move into base rates.

FirstEnergy says cost allocation and rate design will be considered in the initial surcharge filing. Long-term gas supply contract costs will be recovered through the annual ENEC filing, a separate energy-cost recovery proceeding.

The company is seeking a low-interest Department of Energy loan. Its presentation estimates customer savings of about $217 million for each $1 billion of guaranteed financing over 30 years.

Monongahela Power’s capital structure is 50 percent debt and 50 percent equity, FirstEnergy says.

Financing the expansion

FirstEnergy expects to raise $2.8 billion in equity and equity-like securities through 2030, up from $2 billion, and fund about 35 percent of the Maidsville investment with those instruments.

The company raised its forecast for annual compound growth in non-GAAP core earnings per share to 7 percent to 9 percent, targeting the upper half, from a previous range of 6 percent to 8 percent, near its upper end.

Projected annual rate-base growth rose to 11.1 percent from 10.4 percent. FirstEnergy forecasts a $45.5 billion rate base in 2030 with Maidsville, compared with $43.6 billion previously, assuming weighted-average construction work in progress for Maidsville.

Next are the initial surcharge filing and the gas supply and engineering, procurement and construction contracts expected in the fourth quarter of 2026. FirstEnergy plans an early-2027 update on additional generation and temporary power options. Its comprehensive 2027-2031 investment-plan roll-forward is scheduled for February 2027.