The Buildout

American Buildout

Vol. I · No. 1
Covering America’s infrastructure buildout.
UpdatedSunday, September 27, 2026

Buildout Tracker

Paducah American Energy Hub

Buildout Tracker (beta): DOE picked Brookfield and NextEra for a $100 billion, 1.8 GW data center campus with 4.6 GW of dedicated generation at the former Paducah Gaseous Diffusion Plant. No definitive agreements have been announced and no PSC filing is on record.

Buildout TrackerBeta

Paducah American Energy Hub

Developer BrookfieldPower NextEra Energy ResourcesLandowner U.S. DOELoad 1.8 GWStated cost $100BTenant Not named

On July 29, 2026, the Department of Energy selected Brookfield to lease land at its Paducah Site, the former Paducah Gaseous Diffusion Plant in McCracken County, Ky., and build an AI and high-performance computing campus, and selected NextEra Energy to build and own the generation behind it. DOE had sought proposals for the site in a solicitation issued Nov. 4, 2025. The campus is designed for 1.8 GW of utility load, which NextEra says supports more than 1.2 GW of compute. It is paired with up to 2 GW of new natural gas generation and 2.6 GW of battery storage, for 4.6 GW of dedicated resources. Big Rivers Electric Corp. will supply wholesale power and Jackson Purchase Energy Cooperative will provide retail service. The partners put the privately funded investment at $100 billion over 20 years, with about 8,000 construction jobs and 600 permanent jobs. A fact sheet posted by McCracken County lists commercial operation of the data center and batteries as early as 2028 and the gas plant as early as 2032. DOE puts completion at 2031; NextEra puts it at 2032. No data center tenant has been named.

No definitive agreements have been announced. The NextEra/Brookfield release states the project is subject to negotiation and execution of definitive documentation, and both DOE and the release state that the power service agreement requires approval by the Kentucky Public Service Commission. A search of the PSC’s case records on Sept. 27 found no filing tied to the project. The site has been on EPA’s Superfund National Priorities List since 1994, with trichloroethylene and technetium-99 among its contaminants and cleanup forecast through 2065 and likely beyond. On Aug. 6, Gov. Andy Beshear signed Executive Order 2026-494, which requires data center developers to file an energy plan with the state Energy and Environment Cabinet showing they will not raise electric bills, directs the PSC to bar utilities from raising rates to recover data center costs, and directs the cabinet to deny permits where a data center would negatively affect air quality, water use, water quality, water supply, federal jurisdictional wetlands or natural resources. The governor’s release does not name the Paducah project. The county’s FAQ describes the project as in its early stages, with technical and environmental analyses under way and public meetings planned; the county’s project page lists no zoning, tax or other county action.

Project status

Tracker update: Sept. 27, 2026

Status board

Funding Announced

$100B stated, privately funded. No financing terms or signed contracts reported.

Grid & regulatory Not filed

Power service agreement needs Kentucky PSC approval. No PSC case found.

State & local None on record

No county zoning or tax action posted. State EO 2026-494 sets conditions for data center developers.

Delays / withdrawals None reported

No schedule changes or partner exits in DOE, NextEra or county releases.

Stage gauge

  1. 1SolicitationDOE RFP, Nov. 2025
  2. 2Developers selectedJuly 29, 2026
  3. 3Definitive agreementsUnder negotiation
  4. 4PSC approvalNo filing found
  5. 5State & local permitsNone on record
  6. 6ConstructionNot started
  7. 7First operationsTarget: 2028
  8. 8Full buildout2031 (DOE) / 2032 (NextEra)
Complete In progress Not started

Load vs. dedicated generation (GW)

Data center
utility load
1.8
Dedicated
generation
Gas 2.0
Battery 2.6
012344.6
Sources: DOE, NextEra, McCracken County fact sheet.

Water draw (million gal/day)

Historic plant use
Hub, projected
< 5
Historic: up to 30 MGD from the Ohio River. Projected: under 5 MGD for the full project. The data center uses closed-loop cooling; the gas plant needs water for generation and cooling. County fact sheet and FAQ.

By the numbers

$100BStated investment, first 20 years
4.6GWDedicated generation
8,000Construction jobs (est.)
600Permanent jobs (est.)
785Acres leased, per DOE
1994Site listed on EPA Superfund NPL
Superfund
site

DOE leads cleanup under a 1998 Federal Facility Agreement with EPA and Kentucky. Contaminants include TCE, technetium-99, PCBs and uranium. EPA forecasts cleanup through 2065 and likely beyond.

Timeline

  1. Nov 4, 2025DOE seeks proposals for AI data centers and energy projects at the Paducah Site.U.S. DOE
  2. Jan 30, 2026Proposal deadline.U.S. DOE
  3. Jul 2026McCracken County posts project fact sheet and FAQ.McCracken County
  4. Jul 29, 2026DOE selects Brookfield and NextEra. Agreements subject to negotiation; power deal subject to PSC approval.U.S. DOE; NextEra/Brookfield joint release
  5. Aug 4, 2026DOE recaps site event where Secretary Chris Wright announced the hub to site workers.DOE Office of Environmental Management
  6. Aug 6, 2026Gov. Beshear signs Executive Order 2026-494 setting conditions for data center developers.Office of the Governor
  7. Sep 27, 2026Tracker check: no Kentucky PSC case found for the project.psc.ky.gov case search
  8. 2028Target: data center and battery storage online (earliest).McCracken County fact sheet
  9. 2031–32Target: full buildout. Gas generation online as early as 2032.DOE (2031); NextEra, county (2032)
Official action Document posted / tracker check Target date

Figures in conflict

ItemDOENextEra / BrookfieldCounty fact sheet
Completion20312032Gas as early as 2032
Land~785 acres leasedNot stated600 data center, 200 gas, 300 battery (no total stated)
Capacity1.8 GW AI/HPC1.8 GW utility load; 1.2+ GW computeUp to 1,800 MW

Sources

  1. U.S. DOE, Paducah Site solicitation, Nov. 4, 2025
  2. U.S. DOE, partnership announcement, July 29, 2026
  3. U.S. DOE Office of Environmental Management, Aug. 4, 2026
  4. NextEra Energy / Brookfield joint release, July 29, 2026
  5. NextEra Energy Resources project page
  6. McCracken County, Paducah American Energy Hub page
  7. McCracken County, project fact sheet
  8. McCracken County, project FAQ
  9. U.S. EPA Superfund site profile, Paducah Gaseous Diffusion Plant
  10. Kentucky Public Service Commission case records
  11. Office of the Governor, Team Kentucky Update, Aug. 6, 2026
  12. Executive Order 2026-494
Buildout Tracker (beta) follows announced U.S. hyperscale projects from announcement through operation. Built from government records and developer releases only. Status reflects those records as of the update date.
Share
Ad slot · in-article

Leave a Reply