Microsoft Fairwater
Buildout Tracker (beta): Microsoft’s Fairwater campus in Mount Pleasant, Wisconsin is fully operational, with a second facility due in 2028 — after a $3.3 billion first build (a dollar figure, not 3.3 GW), a $5 million incentive redirected to the village, and a residents’ noise lawsuit.
Microsoft Fairwater
Microsoft’s Fairwater campus in Mount Pleasant, Wisconsin — built on the former Foxconn site in Racine County — is operating. Microsoft announced on June 23, 2026 that its first datacenter facility there was complete and fully operational, ahead of schedule, describing it as “the world’s most powerful AI datacenter.” The first facility carries the $3.3 billion price tag Microsoft attached when it announced the project in 2024; the company estimates about $4.7 billion in hyperscale construction spending in Wisconsin between 2024 and 2028. Microsoft has not disclosed the campus’s power capacity in gigawatts. A second facility is under construction immediately next door and is expected online in 2028, by which point Microsoft projects roughly 800 full-time employees in the village.
The buildout has reshaped the village’s finances and drawn its first lawsuit. In late September 2026 Microsoft moved to redirect its $5 million annual development incentive from the 2023 agreement — $4.9 million back to Mount Pleasant for property-tax relief and infrastructure beginning in 2027, and $100,000 to the Racine County Economic Development Corporation. In January 2026 the village approved 15 additional data center buildings on the site. On July 3, 2026, residents filed a class-action lawsuit against Microsoft in U.S. District Court for the Eastern District of Wisconsin, alleging persistent noise — including low-frequency hum from generators and cooling systems — since the facility began operating; Microsoft has said it acknowledged a “tonal humming” in April and added mitigation measures.
Project status
Tracker update: Oct. 2, 2026Status board
~$3.3B first facility (announced 2024); ~$4.7B Wisconsin hyperscale spend planned through 2028.
First facility operating; 15 added buildings approved Jan. 2026; second facility under construction.
Class-action noise suit filed July 2026 in U.S. District Court (E.D. Wis.).
First facility delivered ahead of schedule; no delays or withdrawals reported.
Stage gauge
- 1SiteFormer Foxconn site
- 2Announced$3.3B, 2024
- 3Local approvalVillage approvals
- 4ConstructionFirst facility built
- 5OperationalFully operational, Jun 2026
- 6Expansion OK’d15 buildings, Jan 2026
- 72nd facilityUnder construction
- 82nd onlineExpected 2028
Microsoft investment in Wisconsin ($ billions)
facility
2024–2028
$5M development incentive ($ millions)
(2023 deal)
village
By the numbers
Built on the former Foxconn “Wisconn Valley” site in Mount Pleasant, Racine County.
Timeline
- 2024Microsoft announces a $3.3B Fairwater investment on the former Foxconn site.Microsoft
- Sep 18, 2025Microsoft unveils Fairwater as the “world’s most powerful AI datacenter.”Microsoft
- Jan 26, 2026Mount Pleasant approves 15 additional data center buildings.Village of Mount Pleasant
- Apr 2026Equipment energized; neighbors report humming; Microsoft acknowledges and adds mitigation.Microsoft / court filing
- Jun 23, 2026Microsoft announces the first facility is complete and fully operational, ahead of schedule.Microsoft
- Jul 3, 2026Residents file a class-action noise suit in U.S. District Court (E.D. Wis.).Court filing
- Sep 2026Microsoft redirects its $5M incentive: $4.9M to the village, $0.1M to county EDC.Microsoft / Village
- 2028Second facility expected online; ~800 village jobs projected.Microsoft
Figures in conflict
| Figure | Microsoft / official | Other reports | What’s correct |
|---|---|---|---|
| Campus capacity | Not stated in gigawatts | “3.3 GW” (third-party index) | The “3.3” is the 2024 dollar cost ($3.3B), not gigawatts. |
| Start of operation | Fully operational Jun 2026 | “Online since April” | Equipment energized in April; full operation June 2026. |
| Residents affected | Class reps named in the filing | “~1,000 within 1.5 miles” | A claim in the complaint; the class is not yet certified. |
Sources
- Microsoft — “Microsoft completes construction on first datacenter facility in Mount Pleasant, Wisconsin” (June 23, 2026)
- Microsoft — “Inside the world’s most powerful AI datacenter” (Sept. 18, 2025)
- Microsoft / Village of Mount Pleasant — incentive redirect press release (Sept. 2026)
- Wisconsin Public Radio — “Microsoft to redirect data center incentive back to Mount Pleasant” (Sept. 2026)
- Village of Mount Pleasant Village Board — approval of 15 additional data center buildings (Jan. 26, 2026)
- U.S. District Court, Eastern District of Wisconsin — Residents v. Microsoft Corp., class-action noise complaint (filed July 3, 2026)