Meta Hyperion

Buildout Tracker (beta): Meta’s $50 billion-plus, 5 GW Hyperion campus in Richland Parish, Louisiana, is under construction with three Entergy gas plants approved, while a second, seven-plant power buildout heard by state regulators Oct. 7 awaits a Dec. 16 Public Service Commission vote that consumer and environmental groups are contesting.

Buildout TrackerBeta

Meta Hyperion

Developer Meta / Blue Owl Capital joint venture (80/20) Tenant Meta Platforms Location Holly Ridge, Richland Parish, Louisiana Power 5 GW IT capacity (planned) Stated investment $50 billion+ Status Under construction; seven-plant power plan awaits Dec. 16 vote

Hyperion is Meta’s AI data center campus at Holly Ridge in Richland Parish, Louisiana, announced with Louisiana Economic Development on Dec. 4, 2024, as a $10 billion, 4 million-square-foot project with site work starting that month and construction expected to run through 2030. On Aug. 20, 2025, the Louisiana Public Service Commission voted 4-1 to approve Entergy Louisiana’s settlement to build three combined-cycle gas plants for the site — two in Richland Parish due in late 2028 and one at the Waterford site in St. Charles Parish due in late 2029 — plus new transmission, and authorized up to 1,500 megawatts of solar through an expedited certification. On Oct. 21, 2025, Meta and funds managed by Blue Owl Capital formed a joint venture to develop and own the campus, with the Blue Owl funds holding 80 percent and Meta 20 percent, funding pro rata shares of about $27 billion in estimated development costs, with Meta as the campus lessee. Entergy broke ground on the two Richland Parish plants, including the Franklin Farms Power Station, on Dec. 1, 2025. On July 13, 2026, Meta and the state said the campus would grow to nearly 10 million square feet and 5 gigawatts of IT capacity at an investment of more than $50 billion, with about 7,500 workers at peak construction, 1,000 operational jobs, more than $1.6 billion in contracts to Louisiana businesses to date and $215 million for Entergy’s bill-assistance and energy-efficiency programs.

The expansion depends on a second Entergy Louisiana power buildout, filed with the commission on March 25, 2026, docketed as U-37882 under the state’s Lightning Directive and announced March 27: seven 754-megawatt combined-cycle gas units totaling 5,278 megawatts, three battery storage projects, a 150-mile 500-kilovolt line from Richland Parish to St. Landry Parish with further 500-kV and 230-kV lines, and an output increase at the Waterford 3 nuclear plant. Entergy says Meta will pay the full cost of service and projects about $2 billion in savings for other customers over 20 years. On April 15, 2026, the commission voted 4-1 to set a Lightning Directive schedule that puts the application before the commission at its Dec. 16, 2026, business and executive session, with the Administrative Hearings Division compiling the record for de novo review and no formal recommendation from the administrative law judge. The Alliance for Affordable Energy, Union of Concerned Scientists and Sierra Club intervened; the Sierra Club’s August testimony asked the commission to reject the plan or restructure it so Meta carries 100 percent of its fuel costs, the full cost of the associated transmission line and the stranded-asset risk if Meta leaves before the plants are paid off. On Aug. 12, 2026, the commission voted 3-1 to vacate a subpoena the groups had obtained for Meta’s job and electricity-load calculations. Entergy filed notice of a Sept. 25 term sheet reached with commission staff on Sept. 28, and the parties’ joint prehearing statement set a three-day evidentiary hearing before the administrative law judge to begin Oct. 7. Separately, the Louisiana Department of Environmental Quality held an Oct. 1 public hearing at the Rayville Civic Center on the proposed air permits for Entergy’s Richland Parish 3 & 4 Power Station, with comments due Oct. 5; the EPA’s review periods on the Title V permits for both the Richland Parish 1 & 2 and 3 & 4 stations ended Oct. 5, with Dec. 4 public-petition deadlines. The Sierra Club has asked LDEQ to reclassify the data center’s own air permit, issued to Laidley LLC, as a major source.

Project status

Tracker update: Oct. 16, 2026

Status board

FundingFinanced

Meta / Blue Owl Capital joint venture (Oct. 21, 2025) funds about $27 billion in estimated development costs; Meta’s stated total investment is more than $50 billion. Entergy says Meta pays the full cost of the utility infrastructure.

Local / grid approvalsVote pending

First three gas plants and transmission approved by the LPSC on Aug. 20, 2025 (U-37425). Seven-plant expansion (U-37882) set for hearing Oct. 7; commission consideration scheduled for Dec. 16, 2026. Title V permits for the Richland Parish 1 & 2 and 3 & 4 power stations in EPA petition period to Dec. 4.

Public oppositionContested

Alliance for Affordable Energy, Union of Concerned Scientists and Sierra Club are intervenors in U-37882; Sierra Club testimony urges rejection. Sierra Club also contests the data center’s LDEQ minor-source air permit.

Delays / withdrawalsNone on record

No schedule change, withdrawal or construction halt appears in the official record reviewed for this update.

Stage gauge

  1. 1AnnouncedMeta and LED, Dec. 4, 2024
  2. 2Construction startSite work, December 2024
  3. 3First power approvalLPSC U-37425, Aug. 20, 2025
  4. 4FinancingMeta / Blue Owl JV, Oct. 21, 2025
  5. 5Gas plants break groundRichland Parish, Dec. 1, 2025
  6. 6Expansion to 5 GWMeta, July 13, 2026
  7. 7Expansion power approvalLPSC U-37882; vote set for Dec. 16, 2026
  8. 8First buildings onlineDate not stated
CompleteIn progressNot started

By the numbers

$50 B+Stated investment, up from $10 billion at announcement
5 GWPlanned IT capacity, up from 2 GW
10 MSquare feet of planned development (nearly)
10Entergy gas plants: three approved (2025) plus seven proposed (U-37882)
7,500Workers onsite at peak construction
1,000Operational jobs once completed
Site

The campus is at Holly Ridge in Richland Parish and at its longest extends more than a mile front to back. Meta says the data halls use a closed-loop glycol cooling system with dry cooling for most of the year. The Blue Owl–Meta venture owns the campus; Meta provides construction, administrative and property-management services and will lease it. Entergy’s Franklin Farms Power Station and a second combined-cycle facility are under construction in Richland Parish; the 55-acre Smalling Substation, funded by Meta in its entirety, on which Entergy broke ground June 27, 2025, connects the site to the grid.

Timeline

  1. Dec. 4, 2024Meta and Louisiana Economic Development announce a $10 billion AI data center in Richland Parish. Louisiana Economic Development
  2. April 2025Entergy Louisiana completes first-phase line upgrades delivering 10 MW for construction. Entergy Louisiana
  3. June 27, 2025Entergy Louisiana breaks ground on the Meta-funded, 55-acre Smalling Substation. Entergy Louisiana
  4. Aug. 20, 2025LPSC approves settlement for three combined-cycle gas plants, transmission and up to 1,500 MW of solar, 4-1. LPSC / Entergy Louisiana
  5. Oct. 21, 2025Meta and Blue Owl Capital funds form a joint venture to develop and own Hyperion (80/20). Meta
  6. Dec. 1, 2025Entergy Louisiana breaks ground on the Franklin Farms Power Station and a second Richland Parish gas plant; operational target late 2028. Louisiana Economic Development
  7. March 25, 2026Entergy files U-37882 application for Project Evest generation and transmission under the Lightning Directive. Entergy Louisiana / LPSC
  8. March 27, 2026Entergy announces Meta agreement: seven gas plants (5,200+ MW), batteries, transmission, Waterford 3 uprate; $2 billion savings claim. Entergy Louisiana
  9. April 15, 2026LPSC votes 4-1 to set a Lightning Directive schedule with commission consideration at its Dec. 16, 2026, session. LPSC
  10. April 16, 2026Union of Concerned Scientists criticizes the fast track. Union of Concerned Scientists
  11. July 13, 2026Meta commits more than $50 billion; campus expands to 5 GW and nearly 10 million square feet. Louisiana Economic Development / Meta
  12. July 30, 2026Sierra Club asks LDEQ to reclassify the Laidley LLC data center air permit as a major source. Sierra Club
  13. Aug. 2026Sierra Club files testimony urging the LPSC to reject the seven-plant plan. Sierra Club
  14. Aug. 12, 2026LPSC votes 3-1 to vacate the subpoena to Meta for job and load data; written order Sept. 17. LPSC
  15. Sept. 16, 2026LPSC accepts a Sept. 4 stipulation and vacates an Aug. 6 ALJ ruling in U-37882. LPSC minutes
  16. Sept. 28, 2026Entergy files notice of a Sept. 25 term sheet with commission staff; joint prehearing statement sets Oct. 7 hearing. LPSC docket U-37882
  17. Oct. 1, 2026LDEQ public hearing at the Rayville Civic Center on air permits for Entergy’s Richland Parish 3 & 4 Power Station; comments due Oct. 5. LDEQ notice
  18. Oct. 7, 2026Three-day evidentiary hearing on U-37882 set to begin before the administrative law judge. Joint prehearing statement, U-37882
  19. Dec. 16, 2026LPSC business and executive session; commission consideration of U-37882 scheduled. LPSC 2026 schedule

Sources

  1. Louisiana Economic Development — Meta Selects Northeast Louisiana as Site of $10 Billion AI-Optimized Data Center (Dec. 4, 2024)
  2. Entergy Louisiana — Infrastructure upgrades in Richland Parish, 10 MW for construction (April 2025)
  3. Entergy Louisiana — Receives LPSC approval for major infrastructure investments to support Meta’s data center (Aug. 20, 2025)
  4. Louisiana Public Service Commission — Minutes, Aug. 20, 2025, business and executive session, U-37425 settlement approved 4-1
  5. Entergy Louisiana — Entergy Louisiana breaks ground on key substation to power data center in Richland Parish (June 27, 2025)
  6. Meta — Meta announces joint venture with funds managed by Blue Owl Capital to develop Hyperion data center (Oct. 21, 2025)
  7. Louisiana Economic Development — Entergy Louisiana breaks ground on new generation facilities in Richland Parish (December 2025)
  8. Entergy Louisiana — Application for approval of generation and transmission resources, Project Evest, LPSC Docket U-37882, public redacted (March 25, 2026; third-party copy)
  9. Entergy Louisiana — Entergy Louisiana announces a new agreement with Meta that will deliver an additional $2B in customer savings (March 27, 2026)
  10. Entergy Corp. — Regulatory and other information: U-37882 filing (March 27, 2026) and U-37425 settlement approval (Aug. 20, 2025)
  11. Louisiana Public Service Commission — Transcript, April 15, 2026, business and executive session, U-37882 procedural schedule (Exhibit 14)
  12. Union of Concerned Scientists — Louisiana regulators fast-track 7-gas-plant proposal for Meta data center (April 16, 2026)
  13. Louisiana Economic Development — Meta Commits More Than $50 Billion for North Louisiana Project (July 13, 2026)
  14. Meta Data Centers — Richland Parish Data Center
  15. Sierra Club — Sierra Club urges rejection of Meta gas plant expansion proposal (August 2026)
  16. Louisiana Public Service Commission — Order U-37882-A vacating subpoena to Meta (Sept. 17, 2026; third-party copy)
  17. Louisiana Public Service Commission — Minutes, Sept. 16, 2026, business and executive session (third-party copy)
  18. Entergy Louisiana — Notice of settlement term sheet with LPSC Staff, U-37882 (Sept. 28, 2026; third-party copy)
  19. LPSC Docket U-37882 — Joint prehearing statement setting Oct. 7, 2026, hearing (Sept. 28, 2026; third-party copy)
  20. Louisiana Department of Environmental Quality — Public hearing notice, Entergy Louisiana Richland Parish 3 & 4 Power Station (AI 249365), Oct. 1, 2026
  21. U.S. EPA — Title V operating permit review timeline, Louisiana (Richland 1/2 and 3/4 power stations)
  22. Louisiana Public Service Commission — Minutes, Dec. 17, 2025, adopting the 2026 business and executive session schedule (Dec. 16, 2026)
Share
Ad slot · in-article

Leave a Reply

Your email address will not be published. Required fields are marked *

B

American Buildout Podcast

Episode player

▶
--:-- / --:--
Coming soonAmerican Buildout Podcast