Stargate Abilene

Buildout Tracker (beta): Crusoe’s 1.2 GW Stargate campus in Abilene, Texas is operating for Oracle and OpenAI with six of eight buildings delivered, while a “potential” 600 MW expansion has gone unconfirmed, Microsoft took a 900 MW campus next door, and a state air permit for added on-site power is pending.

Buildout TrackerBeta

Stargate Abilene

Developer Crusoe (on the Lancium Clean Campus) Tenant Oracle (for OpenAI) Location Abilene, Taylor County, Texas Power 1.2 GW, eight buildings Stated investment $15B joint venture Status Operating; six of eight buildings delivered

Stargate Abilene is Crusoe’s eight-building AI data center campus on the Lancium Clean Campus in Abilene, in Taylor County, Texas, leased to Oracle, which runs it for OpenAI as the first Stargate site. Crusoe began construction in June 2024 and on March 18, 2025, announced a second phase of six more buildings, bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts, with each building designed to run up to 50,000 Nvidia GB200 NVL72 systems. On May 21, 2025, Crusoe, Blue Owl Capital and Primary Digital Infrastructure announced the second phase of a $15 billion joint venture to fund the campus. The Abilene City Council approved 85 percent, 10-year property tax abatements for the site in February 2025 and on Aug. 28, 2025, split them into per-building agreements covering all eight buildings. Crusoe said on Sept. 30, 2025, that the first phase was running on Oracle Cloud Infrastructure, after Oracle began delivering GB200 racks in June 2025.

On its Sept. 10, 2026, earnings call, Oracle said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered, that it delivered 131,000 GPUs at Abilene during the quarter, and that OpenAI’s GPT-6 Astra was trained at the site. Oracle said on June 25, 2026, that construction had logged nearly 20 million worker hours with up to 9,000 workers onsite. The additional 600-megawatt expansion near the campus that OpenAI described as “potential” on Sept. 23, 2025, has not been announced as proceeding by OpenAI, Oracle or Crusoe. On March 27, 2026, Crusoe announced a separate 900-megawatt campus for Microsoft on adjacent land, with two buildings and its own on-site power plant, taking projected capacity across the full Abilene site to 2.1 gigawatts; Crusoe expects the first Microsoft building to be energized in mid-2027. A Crusoe application to the Texas Commission on Environmental Quality for additional on-site power generation to serve the data center buildings, air permit No. 182126, is pending.

Project status

Tracker update: Oct. 14, 2026

Status board

FundingFinanced

Second phase of a $15 billion joint venture among Crusoe, Blue Owl Capital and Primary Digital Infrastructure announced May 21, 2025, funding all eight buildings.

Local / grid approvalsPermit pending

City of Abilene approved 85 percent, 10-year tax abatements (Feb. 2025; per-building agreements Aug. 28, 2025). TCEQ air permit No. 182126 for added on-site generation is pending.

Public oppositionNone on record

No lawsuit, referendum or organized opposition appears in the official record reviewed for this update.

Delays / withdrawalsExpansion not confirmed

The 600 MW “potential” expansion OpenAI cited Sept. 23, 2025, has not been announced as proceeding; Crusoe’s adjacent land went to a 900 MW Microsoft campus on March 27, 2026.

Stage gauge

  1. 1Construction startCrusoe, June 2024
  2. 2Tax abatementsCity of Abilene, Feb. 2025
  3. 3Phase 2 to 1.2 GWSix buildings, March 18, 2025
  4. 4Financing$15B JV, May 21, 2025
  5. 5First phase liveOn OCI, Sept. 30, 2025
  6. 6Buildings delivered6 of 8, 618 MW (Sept. 10, 2026)
  7. 7Added on-site powerTCEQ permit 182126 pending
  8. 8Full 1.2 GWFinal two buildings; date not stated
CompleteIn progressNot started

By the numbers

1.2 GWCampus capacity at full buildout
618 MWDelivered to Oracle, six of eight buildings (Sept. 10, 2026)
8Buildings, about 4 million sq. ft. total
$15 BJoint venture: Crusoe, Blue Owl, Primary Digital
85%City property tax abatement, 10 years per building
20 MConstruction worker hours (Oracle, June 25, 2026)
Site

The campus sits on the Lancium Clean Campus in Abilene. Each of the eight buildings is designed for up to 50,000 GB200 NVL72 systems on a single network fabric. Crusoe’s separate 900 MW Microsoft campus, with two buildings and a 900 MW on-site power plant, is on adjacent land; Crusoe’s pending TCEQ application covers additional generation for on-site use at the data center buildings.

Timeline

  1. June 2024Crusoe begins construction on the Lancium Clean Campus. Crusoe
  2. Jan. 21, 2025OpenAI, SoftBank, Oracle and MGX announce Stargate; buildout “starting in Texas.” OpenAI
  3. Feb. 2025Abilene City Council approves tax abatements for the campus. City of Abilene
  4. March 18, 2025Crusoe starts six more buildings, taking the campus to 1.2 GW. Crusoe
  5. May 21, 2025Second phase of $15 billion joint venture announced. Crusoe / Blue Owl / Primary Digital
  6. July 22, 2025OpenAI and Oracle agree to 4.5 GW of additional Stargate capacity; Abilene cited as Stargate I. OpenAI
  7. Aug. 28, 2025Council hearing on per-building abatement agreements for all eight sites. City of Abilene
  8. Sept. 23, 2025OpenAI announces five new Stargate sites and a “potential” 600 MW expansion near Abilene. OpenAI
  9. Sept. 30, 2025Crusoe says first phase is live on Oracle Cloud Infrastructure. Crusoe
  10. March 27, 2026Crusoe announces adjacent 900 MW campus for Microsoft; full site projected at 2.1 GW. Crusoe
  11. June 25, 2026Oracle cites nearly 20 million worker hours and up to 9,000 workers onsite. Oracle
  12. Sept. 10, 2026Oracle reports six of eight buildings, 618 MW, delivered; GPT-6 Astra trained at Abilene. Oracle Q1 FY27 earnings call

Sources

  1. OpenAI — Announcing The Stargate Project (Jan. 21, 2025)
  2. Crusoe — Crusoe expands AI data center campus in Abilene to 1.2 gigawatts (March 18, 2025)
  3. Crusoe — Crusoe, Blue Owl Capital and Primary Digital Infrastructure enter second phase of $15 billion joint venture (May 21, 2025)
  4. OpenAI — Stargate advances with 4.5 GW partnership with Oracle (July 22, 2025)
  5. City of Abilene — City Council agenda: Lancium data center tax abatement agreements (Aug. 28, 2025)
  6. City of Abilene — Tax abatement agreements, Lancium LLC and Abilene DC 1–10 (agreement texts)
  7. OpenAI — OpenAI, Oracle and SoftBank expand Stargate with five new AI data center sites (Sept. 23, 2025)
  8. Crusoe — Crusoe announces flagship Abilene data center is live (Sept. 30, 2025)
  9. Crusoe — Crusoe announces new 900 MW AI factory campus in Abilene to support Microsoft (March 27, 2026)
  10. Oracle — Facts About Construction Safety in Abilene (June 25, 2026)
  11. Oracle — Q1 FY2027 results release (Sept. 10, 2026)
  12. Oracle — Q1 FY2027 earnings call remarks on Abilene (Sept. 10, 2026; transcript)
  13. Texas Commission on Environmental Quality — Plain-language summary, pending air permit No. 182126, Crusoe Energy Systems LLC, Longhorn Data Center, Abilene
Share
Ad slot · in-article

Leave a Reply

Your email address will not be published. Required fields are marked *

B

American Buildout Podcast

Episode player

▶
--:-- / --:--
Coming soonAmerican Buildout Podcast