TerraVolt Declo Campus
Buildout Tracker (beta): TerraVolt Holdings' planned campus outside Declo, Cassia County, Idaho — options on about 1,077 acres signed Oct. 23, 2026, an initial 240 MW of islanded on-site gas generation backed by a firm 55,000 MMBtu-a-day supply, and no county or state filing yet on record.
TerraVolt Declo Campus
TerraVolt Holdings, the Tustin, Calif. company that renamed itself from CalEthos on June 30, 2026, signed two option agreements dated Oct. 23, 2026 with Wickel Land Company LLP for about 1,077 acres outside Declo in Cassia County, Idaho, and reported them in a Form 8-K on Oct. 30. The land is split into 903.3 acres of “cash parcels” and 174.1 acres of “stock parcels,” both priced at $30,000 an acre: about $27.1 million in cash and about $5.2 million by a two-year convertible note at $5.00 a share secured by a mortgage on the stock parcels. TerraVolt paid a $150,000 option fee, half of it nonrefundable, into escrow at TitleOne Corporation. The options run to Oct. 23, 2027 with one six-month extension for $75,000, both options must be exercised together, and the clock stops during litigation or a government moratorium. The agreements let TerraVolt pursue zoning amendments, conditional use permits, development agreements and water-right changes at its own cost during the option period, and let it walk away with the refundable half if it verifies a zoning, environmental, water-rights, title or permitting problem.
The plan is a master-planned campus with an initial 240 megawatts of on-site natural gas generation designed to operate independently of the local grid, fed under a firm gas agreement for 55,000 MMBtu a day that CalEthos signed May 11, 2026 with an unnamed gas marketer. The company paid about $3.83 million to reserve that supply, posted a $6 million standby letter of credit to the supplier in August, must give a start-date notice by April 30, 2028 and must begin taking gas by July 31, 2029 for a three-year term. TerraVolt would sell building sites to data center operators and supply power, fiber, water and wastewater service under long-term agreements, with low-water cooling required on every building as a condition of each sale. The company has three employees, reported $10.7 million in cash at June 30, 2026, a $15 million related-party note from SFO IDF due April 2028, and a going-concern warning in its latest quarterly report. Its annual report targets land-use approvals by the end of 2026 and construction approvals by the second quarter of 2027. As of Oct. 31, no application, hearing or agenda item for the site appeared on Cassia County’s planning pages and no Idaho DEQ permit application was located.
Project status
Tracker update: Oct. 31, 2026Status board
$10.7 million cash at June 30, 2026; $15 million SFO IDF note at 8 percent due April 30, 2028; up to $37.5 million owed to SFO IDF contingent on Phase 1 parcel sales. No offtake, site-sale or construction financing disclosed. 10-Q: substantial doubt about the company’s ability to continue as a going concern.
No Cassia County land-use application or hearing and no Idaho DEQ permit application located. Company targets: rezoning in under 12 months, land-use approvals by year-end 2026, environmental reports before end of 2026, construction approvals by Q2 2027. Islanded design; no utility interconnection sought.
No public comment, petition or litigation on record. The option agreements toll the option period during any government moratorium or litigation.
The company let its prior Imperial County, Calif. purchase option lapse in July 2025 before turning to Idaho, per its 10-K.
Stage gauge
- 1Gas supplyFirm 55,000 MMBtu/d, May 11, 2026
- 2Site controlOption agreements, Oct. 23, 2026
- 3Due diligenceOption period to Oct. 23, 2027
- 4County land useTarget year-end 2026, per 10-K
- 5State permitsEnvironmental filings before end of 2026, per 10-K
- 6Land purchaseBoth options exercised together
- 7Construction approvalsTarget Q2 2027, per 10-K
- 8Gas deliveriesStart no later than July 31, 2029
By the numbers
Ten parcels in Township 10 South, Range 25 East, Boise Meridian, outside Declo, zoned Multiple-Use, along State Highway 81 near Interstate 84, long-haul fiber routes and the Williams Northwest Pipeline. The cash parcels total an estimated 903.3 acres across eight parcels, the largest 615.6 acres; the stock parcels are two parcels of 111 and 63.1 acres. Final acreage is set by an ALTA survey. The company’s annual report describes the land as flat agricultural ground with secured agricultural water rights and says it expects ongoing campus water use to be mainly domestic and fire protection. The capacity figure has moved in company statements: 300 to 350 MW in the March 2026 annual report, 200 to 240 MW in the May release, 240 MW in October.
Timeline
- July 2025CalEthos lets its Imperial County, Calif. purchase option lapse.10-K
- March 31, 202610-K describes a “Northwestern U.S.” campus with a gas contract negotiated for 300 to 350 MW; cash $287,000 at Dec. 31, 2025.10-K
- April 2026SFO IDF advances $15 million at 8 percent, due April 30, 2028, with a warrant for 6 million shares at $0.50.10-Q
- May 11, 2026Firm gas supply agreement, 55,000 MMBtu a day, for a Southeast Idaho campus of 200 to 240 MW; reservation fee about $3.83 million paid.8-K / 10-Q
- June 30, 2026CalEthos becomes TerraVolt Holdings, Inc.; ticker GEDC unchanged.8-K, July 7
- Aug. 14, 202610-Q: cash $10.7 million, going-concern doubt, land “not yet secured,” site control expected within 60 days; $6 million standby letter of credit issued to the gas supplier.10-Q
- Oct. 23, 2026Option agreements with Wickel Land Company LLP for 903.3 and 174.1 acres at $30,000 an acre; $150,000 option fee; options expire Oct. 23, 2027.8-K exhibits 10.1, 10.2
- Oct. 30, 20268-K and release announce the option: 240 MW islanded campus, low-water cooling condition, county and state permitting to follow.8-K / release
- Year-end 2026Company target for land-use approvals and environmental report filings.10-K
- Q2 2027Company target for construction approvals.10-K
- Oct. 23, 2027Options expire unless extended six months for $75,000.8-K
- April 30, 2028Deadline for start-date notice to the gas supplier; deliveries must begin by July 31, 2029.10-Q
Sources
- TerraVolt Holdings, Inc. — Form 8-K, Item 1.01, Option Agreements with Wickel Land Company LLP (filed Oct. 30, 2026)
- Option Agreement, Cash Parcels, effective Oct. 23, 2026 (Exhibit 10.1)
- Option Agreement, Stock Parcels, effective Oct. 23, 2026 (Exhibit 10.2)
- TerraVolt Holdings — Secures Option on 1,077-Acre Site in Idaho for 240 MW Gas-Powered Data Center Campus (Oct. 30, 2026)
- TerraVolt Holdings, Inc. — Form 10-Q for the quarter ended June 30, 2026 (filed Aug. 14, 2026)
- TerraVolt Holdings, Inc. — Form 8-K, name change from CalEthos, Inc. (filed July 7, 2026)
- CalEthos, Inc. — Form 8-K, natural gas supply agreement (filed May 11, 2026)
- CalEthos, Inc. and TerraVolt Infrastructure, Inc. — Natural Gas Supply Agreement release (May 11, 2026)
- CalEthos, Inc. — Form 10-K for fiscal 2025 (filed March 31, 2026)