Buildout Tracker (beta): the Stratos Project Area in Box Elder County, Utah — a 40,000-acre MIDA project area with a 3 GW first phase and about 9 GW projected, approved by MIDA and the county in spring 2026, now facing a referendum lawsuit and a protested 1,712 acre-foot water right change filed Oct. 15.

Buildout TrackerBeta

Stratos Project Area

Developer O’Leary Digital Utah Development Company, LLC (master developer); O’Leary Digital and West GenCo named by MIDA; Kevin O’Leary, lead investor Authority Military Installation Development Authority (MIDA) project area; Box Elder County consent by Resolutions 26-11 and 26-12 Location About 40,000 acres of private land in Hansel Valley, western unincorporated Box Elder County, in three sites Power Phase 1 committed 3 GW; about 9 GW projected at buildout; dedicated on-site generation; water filing describes a steam plant rated at 7,500 MW Stated investment Not disclosed; developer commits $16.2 million up front and all public infrastructure Status MIDA and county approvals in hand; referendum suit pending; water right change protested, comment to Dec. 1; no air permit filed

MIDA’s board created the roughly 40,000-acre Stratos Project Area in Hansel Valley on April 24, 2026, adopting the project area plan, development standards, an energy sales-and-use tax ordinance and a 30-year development agreement with O’Leary Digital Utah Development Company, LLC, each by unanimous vote. Box Elder County consented on May 4 by Resolutions 26-11 and 26-12 after deferring the vote twice and reviewing more than 2,500 comments, 300 of them from county residents. The interlocal agreement caps noise at 55 decibels at the data center and power plant, requires dark-sky compliance, ties building heights to county fire response capacity with a new fire truck every 10 years if exceeded, and seats a local landowner on the design review committee. The project area plan commits a 3-gigawatt first phase on dedicated on-site generation and projects about 9 gigawatts at buildout; the development agreement gives the developer five years to submit a Phase 1 plan capable of at least 3 gigawatts, pays the developer 80 percent of compute-complex tax revenue with 20 percent retained by MIDA, and bars either party from terminating or seeking damages. MIDA projects about 2,000 permanent jobs and county revenue of $30 million a year at Phase 1 and $108 million a year at buildout.

Opposition has run through the referendum process, the courts and the state water office. Two groups filed referendum applications May 8 and 11; the county attorney rejected both on May 28 as administrative actions, and six sponsors sued the County Commission, its three commissioners, the attorney, clerk and auditor in First District Court on June 3 (Civ. No. 260100091), asking the court to order the applications processed. The county adopted Ordinance 654 on June 10, a 180-day pause on new data center and data center power plant applications in the unincorporated county that does not reach the MIDA area, where the county has ceded land-use authority for 50 years. The developer’s first water right change application, filed March 25, was withdrawn May 6. On Oct. 15 an affiliate, O’Leary Digital Utah DC Sub I, LLC, under contract to buy Bar H Ranch’s 1904-priority right, filed change application a55167 to move 1,712 acre-feet from Salt Wells Spring Stream irrigation to “Wonder Valley Power,” a “steam generation power plant, rated at 7500 MW,” and a data center campus, consuming no more than 1,009 acre-feet; the record already shows it protested, with publication Nov. 4 to 11 and the protest period ending Dec. 1. The Governor’s Office says no Division of Air Quality notice of intent has been filed.

Project status

Tracker update: Nov. 1, 2026

Status board

FundingDeveloper-funded; no financing disclosed

No lenders, tenants or offtake disclosed. Developer commits $16.2 million up front and all public infrastructure. Development agreement returns 80 percent of compute-complex property tax revenue to the developer for the 30-year term; MIDA levies a 0.5 percent municipal energy tax on data center campuses.

Local / grid approvalsMIDA approved; state permits pending

MIDA Resolutions 2026-06 through -09 and Ordinance 2026-01 (April 24); county Resolutions 26-11 and 26-12 (May 4). Water right change a55167 filed Oct. 15, status Unapproved. No air quality notice of intent, water quality or drinking water filing on record. Off-grid design; no utility interconnection described.

Public oppositionReferendum suit; water protests

Referendum applications rejected May 28; six sponsors sued June 3 in First District Court. Water application a55167 shows “Protested” with the comment period open to Dec. 1. More than 2,500 comments to the county before the May 4 vote.

Delays / withdrawalsWater filing withdrawn, refiled

County consent vote moved from April 24 to April 27, then to May 4. First water right change application (March 25) withdrawn May 6; refiled Oct. 15. MIDA’s CFO told the board June 26 the project area has no revenue yet.

Stage gauge

  1. 1MIDA project areaPlan, standards, tax, agreement, April 24, 2026
  2. 2County consentResolutions 26-11, 26-12, May 4, 2026
  3. 3Referendum suitFirst District Court, filed June 3, 2026
  4. 4Water righta55167, protest period to Dec. 1, 2026
  5. 5Air permitNo notice of intent filed
  6. 6Phase 1 planDue within five years of April 24, 2026
  7. 7ConstructionNot started
  8. 8Phase 1 power3 GW committed
CompleteIn progressNot started

By the numbers

3GWPhase 1 commitment; about 9 GW projected at buildout
40,000Acres in the MIDA project area, three sites
1,712Acre-feet sought in water right change a55167; 1,009 consumed
$16.2MUp-front developer payment to the county
2,500+Comments to the County Commission before the May 4 vote
30yrsDevelopment agreement term; 50-year MIDA land-use jurisdiction
Site

About 40,000 acres of privately held vacant land in Hansel Valley, split into three sites: one for energy generation and the data center campus, two reserved for manufacturing, retail, hotels and public works. MIDA’s board summary cites direct access to the Ruby Pipeline; the water application names the plant “Wonder Valley Power” and describes a steam generation plant rated at 7,500 MW drawing from an existing pond on Salt Wells Spring Stream, with return flows toward the Great Salt Lake. The Governor’s Office describes closed-loop dry cooling with “no continuous water draw” and a nearest data center about 10 miles from the lake. Agricultural leasebacks for grazing and farming, conservation buffers and open space are written into the plan.

Timeline

  1. March 25, 2026First water right change application filed with the Division of Water Rights.Governor’s Office FAQ
  2. April 24, 2026MIDA Board adopts the Stratos Project Area Plan, development standards, development agreement, interlocal agreement and energy tax ordinance, all unanimously; Kevin O’Leary speaks as lead investor.MIDA
  3. April 27, 2026County Commission defers its consent vote after public comment.County release
  4. May 4, 2026County adopts Resolutions 26-11 (consent) and 26-12 (interlocal); MIDA adopts the project area plan.County / MIDA
  5. May 6, 2026Developer withdraws the March 25 water application, intending to refile.Governor’s Office FAQ
  6. May 8–11, 2026Two groups file three referendum applications on Resolutions 26-11 and 26-12.County referendum page
  7. May 28, 2026County attorney rejects both applications as administrative, not legislative; auditor’s impact statement cites $5.4 million a year in guaranteed revenue.County
  8. June 3, 2026Six sponsors sue the County Commission in First District Court, Civ. No. 260100091.Complaint as filed
  9. June 10, 2026County adopts Ordinance 654, a 180-day pause on new data center applications; Stratos exempt.County
  10. June 26, 2026MIDA CFO: Stratos has no revenue yet and minimal expenses.MIDA
  11. Oct. 15, 2026O’Leary Digital Utah DC Sub I files change application a55167: 1,712 acre-feet for a 7,500 MW steam plant and data center campus; record marked protested.Division of Water Rights
  12. Nov. 4–11, 2026Water application advertised in the Tremonton Leader.Division of Water Rights
  13. Dec. 1, 2026Protest period on a55167 ends.Division of Water Rights
  14. Dec. 7, 2026Ordinance 654’s 180 days run out unless the county adopts a data center ordinance, extends or repeals it.Ordinance 654
  15. April 24, 2031Deadline for the Phase 1 plan under the development agreement.Development agreement §4(b)

Sources

  1. MIDA — Stratos Project Area page and document library
  2. MIDA — April 24, 2026 Board Meeting Highlights
  3. MIDA — Resolution 2026-06 Enacting the Stratos Project Area Plan (April 24, 2026)
  4. MIDA and O’Leary Digital Utah Development Company, LLC — Development Agreement (April 24, 2026)
  5. MIDA and Box Elder County — Interlocal Cooperation Agreement (executed)
  6. MIDA — Stratos press release (May 4, 2026)
  7. Box Elder County — Box Elder County Authorizes MIDA to Initiate Stratos Project (May 4, 2026)
  8. Box Elder County — Stratos Project Referendum Information, including the County Attorney’s determination and fiscal and legal impact statements
  9. Williams et al. v. Box Elder County Commission et al., Complaint, First District Court, Civ. No. 260100091 (June 3, 2026; copy hosted by the sponsors)
  10. Box Elder County — Commission Adopts Temporary 180-Day Land Use Regulation for Data Centers (June 10, 2026)
  11. Box Elder County — Ordinance No. 654
  12. Utah Division of Water Rights — Change Application a55167, Water Right 13-2 (filed Oct. 15, 2026)
  13. Office of the Governor — Frequently Asked Questions, Stratos Project Area
  14. MIDA — June 26, 2026 Board Meeting Highlights