Polaris Forge 2

Buildout Tracker (beta): Applied Digital's Polaris Forge 2 near Harwood, N.D. — a $3 billion campus with a 200 MW, roughly $5 billion lease to Oracle, $2.15 billion of project notes closed in March 2026, a settled annexation fight with Fargo, and initial operations expected to lift the company's North Dakota delivered load to 300 MW by the end of 2026.

Buildout TrackerBeta

Polaris Forge 2

Developer Applied Digital Corp. (Nasdaq: APLD), Dallas; project entity APLD ComputeCo 2 LLC Tenant Oracle, per Applied Digital’s March 10, 2026 8-K; approximately 15-year, 200 MW lease signed Oct. 22, 2025, about $5 billion in base-term revenue Location More than 900 contracted acres near Harwood, north of Fargo; Applied Digital owns the 303-acre west half of Section 3, T140N R49W Power Cass County Electric Cooperative with Minnkota Power Cooperative; initial 280 MW announced, 200 MW leased, 1 GW potential through the tenant’s 800 MW right of first refusal Stated investment $3 billion; $2.15 billion of 6.75 percent senior secured notes due 2031 issued at the project level Status Under construction; initial operations expected to lift North Dakota delivered IT load to 300 MW by end of 2026; full 200 MW early 2027

Applied Digital announced Polaris Forge 2 on Aug. 18, 2025 as a $3 billion, 280-megawatt campus on more than 900 contracted acres near Harwood, with groundbreaking in September 2025, initial capacity in 2026 and full capacity in early 2027, power through Cass County Electric Cooperative and Minnkota Power Cooperative, and more than 200 permanent jobs at full operation. Harwood’s council gave first reading to a rezoning from agricultural to light industrial on Sept. 2, 2025 after moving the hearing to the Community Center to hold 20 speakers, approved a building permit contingent on second reading, and voted to oppose Fargo’s attempt to annex the site. Fargo had taken the annexation into executive session on Sept. 29 and Nov. 10 and noticed hearings on the 303.23-acre west half of Section 3, owned by Applied Digital, and the 256.87-acre east half, owned by Fercho Properties; on Nov. 24, 2025 the commission voted 5-0 for a 20-year agreement under which Fargo withdraws its annexation of the Applied Digital parcel and Harwood leaves the Fercho parcel alone, with Fargo’s mayor saying the annexation had been meant as leverage over infrastructure and that Harwood would now negotiate on fire and sewer needs.

On Oct. 22, 2025 the company signed an approximately 15-year lease with a U.S.-based investment-grade hyperscaler for 200 MW of critical IT load, about $5 billion in contracted revenue over the base term, two five-year renewal options, take-or-pay and non-cancellable, with a right of first refusal on a further 800 MW that would fill the campus to 1 GW; its March 10, 2026 8-K names the tenant as Oracle. That filing closed $2.15 billion of 6.750 percent senior secured notes due March 15, 2031, issued by APLD ComputeCo 2 LLC at 98 percent of par through Goldman Sachs, secured by first-priority liens on the project and its equity, backed by an Applied Digital completion guarantee, with proceeds dedicated to the 200 MW build, project accounts and a debt service reserve. The 10-K for the year ended May 31, 2026 puts initial capacity in the second half of calendar 2026 and full capacity in early 2027 and notes that lessees may terminate for significant construction delays. The company’s Oct. 7, 2026 release says initial operations at Harwood should bring its North Dakota delivered IT load to 300 MW by the end of 2026, with the Ellendale campus at 250 MW live, and that it signed a power purchase agreement after quarter end with Base Electron for about 1,200 MW of natural gas generation in the state.

Project status

Tracker update: Nov. 3, 2026

Status board

FundingLease and project notes in place

$2.15 billion 6.75 percent senior secured notes due 2031 closed March 10, 2026 to fund the 200 MW, with a company completion guarantee. Company-wide at Aug. 31, 2026: $6.4 billion debt, $3.7 billion cash and restricted cash, $3.67 billion construction in progress.

Local / grid approvalsZoning advanced; annexation settled

Harwood first reading of Ag-to-Light Industrial rezoning Sept. 2, 2025; building permit contingent on second reading. Fargo–Harwood 20-year boundary agreement Nov. 24, 2025. Power agreement with Cass County Electric and Minnkota described as in final stages in Aug. 2025; executed agreement not located.

Public oppositionContested at hearing; resolved locally

Twenty speakers at Harwood’s rezoning hearing. Fargo’s annexation bid, aimed at leverage over infrastructure, withdrawn under the Nov. 24 agreement. No litigation or petition on record.

Delays / withdrawalsNone on record

Schedule unchanged across filings: initial capacity second half of 2026, full 200 MW early 2027. Lease allows tenant termination for significant construction delays.

Stage gauge

  1. 1Announced$3B, 280 MW, Aug. 18, 2025
  2. 2Local zoningHarwood first reading, Sept. 2, 2025
  3. 3Lease200 MW, ~15 years, Oct. 22, 2025; Oracle
  4. 4Annexation settledFargo–Harwood agreement, Nov. 24, 2025
  5. 5Project financing$2.15B notes, March 10, 2026
  6. 6ConstructionTwo buildings under way
  7. 7Initial operationsN.D. load to 300 MW by end of 2026
  8. 8Full 200 MWEarly 2027; 800 MW ROFR to 1 GW
CompleteIn progressNot started

By the numbers

200MWLeased critical IT load; 280 MW announced, 1 GW potential
$5BContracted base-term revenue over about 15 years
$2.15BSenior secured notes, 6.75 percent, due 2031
900+Acres contracted near Harwood
1.18Projected PUE; near-zero water consumption
200+Full-time jobs at full operation
Site

The campus sits north of Fargo in Harwood’s jurisdiction, with Applied Digital holding the 303.23-acre west half of Section 3, Township 140 North, Range 49 West, and Fercho Properties the 256.87-acre east half; Harwood’s Ordinance 2025-42 annexed about 785 acres in the same township and range in June 2025 on petition of owners holding three-quarters of assessed value, with no protests. The initial lease covers two buildings designed at a projected PUE of 1.18 with the company’s waterless cooling. Power is to come through Cass County Electric Cooperative, a member-owned distribution cooperative, with Minnkota as wholesale supplier; at the company level Applied Digital holds about a 10 percent stake in Base Electron, which is developing front-of-the-meter gas generation in the Dakotas under a roughly 1,200 MW power purchase agreement signed in the fall of 2026.

Timeline

  1. June 2, 2025Harwood adopts Ordinance 2025-42 annexing about 785 acres in T140N R49W.Harwood ordinance
  2. Aug. 18, 2025Applied Digital announces Polaris Forge 2: $3 billion, 280 MW, 900+ acres, groundbreaking in September.Applied Digital
  3. Sept. 2, 2025Harwood council hears 20 speakers, gives first reading to the rezoning, votes to oppose Fargo annexation.Harwood minutes
  4. Sept. 29, 2025Fargo commission enters executive session on annexation with Harwood and Applied Digital.Fargo minutes
  5. Oct. 22, 2025Lease signed: ~15 years, 200 MW, ~$5 billion, ROFR on 800 MW; two buildings online 2026, 200 MW in 2027.8-K
  6. Nov. 10, 2025Fargo notices annexation hearings on 303.23 and 256.87 acres in Section 3.Fargo agenda
  7. Nov. 24, 2025Fargo approves 20-year agreement with Harwood, 5-0, withdrawing annexation of the Applied Digital parcel.Fargo minutes
  8. March 10, 2026$2.15 billion 6.75 percent senior secured notes due 2031 close; filing names Oracle as tenant.8-K
  9. July 29, 202610-K: initial capacity second half of 2026, full capacity early 2027; lease take-or-pay, non-cancellable.10-K
  10. Oct. 7, 2026Q1 FY2027: Harwood initial operations to bring N.D. delivered load to 300 MW by year-end; Base Electron PPA ~1,200 MW.Earnings release
  11. Dec. 31, 2026Company target for initial operations at Polaris Forge 2.Earnings release
  12. Early 2027Full 200 MW capacity.10-K
  13. March 15, 2031Notes mature.8-K

Sources

  1. Applied Digital — Applied Digital to Break Ground on $3 Billion Polaris Forge 2 (Aug. 18, 2025)
  2. Applied Digital — Form 8-K Ex. 99.1, lease for Polaris Forge 2 (Oct. 22, 2025)
  3. Applied Digital — Form 8-K Ex. 99.2, proposed $2.15 billion senior secured notes (March 2, 2026)
  4. Applied Digital — Form 8-K, Item 1.01, $2.15 billion 6.750% Senior Secured Notes due 2031; campus “currently leased to Oracle” (March 10, 2026)
  5. Applied Digital — Form 10-K for fiscal year ended May 31, 2026 (July 29, 2026)
  6. Applied Digital — Fiscal Q1 2027 earnings release (Oct. 7, 2026)
  7. Applied Digital — Form 10-Q for quarter ended Aug. 31, 2026 (Oct. 7, 2026)
  8. City of Harwood — City Council Regular Meeting minutes, Sept. 2, 2025
  9. City of Harwood — Ordinance 2025-42, annexation (June 2, 2025)
  10. City of Fargo — City Commission minutes, Nov. 24, 2025 (annexation agreement with Harwood)
  11. City of Fargo — City Commission agenda, Nov. 10, 2025
  12. City of Fargo — City Commission minutes, Sept. 29, 2025