Nebius Independence AI Factory
Buildout Tracker (beta): Nebius' AI factory in Independence, Mo. — 398 acres, up to 1.2 GW, Chapter 100 bonds capped at $150.6 billion with a 98 percent abatement through 2046, under construction since May 2026, and a city that has since put a moratorium and a special use permit regime on every data center after it.
Nebius Independence AI Factory
Nebius, Inc. bought about 398 acres in the EastGate Commerce Center from NorthPoint Development in late 2025 and asked Independence for a Chapter 100 plan covering a multi-building data center campus of about 2.1 million square feet and roughly 800 megawatts, built in stages over three to five years on land already zoned for industrial and business park use. After a Feb. 16, 2026 public hearing, the City Council on March 2 approved Ordinance 19791 by 5-2, authorizing two series of taxable industrial development revenue bonds not to exceed $150.632 billion combined, abating real property tax about 98 percent and personal property tax 90 percent from 2026 through 2046, exempting construction materials from sales tax, and projecting payments in lieu of taxes of $651.5 million to the city, school districts and other jurisdictions over the term, with no city appropriation. Nebius broke ground May 12 with ARCO National Construction and told shareholders the Missouri site is expected to be operational in 2027; its project page puts campus capacity at up to 1.2 GW across four buildings and its workforce at about 1,200 construction and 130 permanent jobs. The city says power will come from Independence Power & Light through a new privately financed plant at the retired Blue Valley Power Plant site, 200 MW at first and 800 MW at full operation plus a 300 MW reserve required by the Southwest Power Pool, with Nebius paying the full cost of its electricity and the city and IPL taking on no debt.
The project changed the city’s rules for everything after it. On July 6 the council voted 7-0 for 180-day moratoria on processing applications for data processing facilities and for battery storage, excluding projects already submitted or approved. On Oct. 5 it adopted Ordinance 19850 by 6-0, a Unified Development Ordinance amendment that allows small facilities in commercial and light industrial districts, confines major facilities to the I-1 district under a special use permit, and sets 100-foot setbacks, a 500-foot separation from homes, schools, parks, daycares, hospitals and places of worship, 100-foot buffers, closed-loop or equivalent cooling, and generator testing limits; projects holding building permits, final site plan approval or other entitlements before the effective date are exempt. Recall petitions against District 1 Councilmember John Perkins drew a July 2 lawsuit from three residents in Jackson County Circuit Court seeking to keep the Sept. 1 recall question off the ballot. Nebius says closed-loop cooling will hold recurring water use to 400,000 to 640,000 gallons a year at full build-out, that noise is modeled at 45 decibels by day and 41 at night at the nearest home, and that the city expects payments to begin in 2028.
Project status
Tracker update: Nov. 2, 2026Status board
Ordinance 19791, March 2, 2026, 5-2: two series of taxable industrial development revenue bonds, combined cap $150.632 billion; real property abated about 98 percent, personal property 90 percent, 2026–2046; PILOTs estimated at $651.5 million. Nebius Group reports group capex of $5.7 billion in Q2 2026 and no site-level figure.
Data centers an allowed use under existing zoning; no rezoning required. Public hearing Feb. 16; plan approved March 2; groundbreaking May 12. Power via Independence Power & Light from a new plant at the Blue Valley site, 200 MW initially, 800 MW at full operation; IPL plans initial power in the second half of 2026. No PSC or SPP record for the plant retrieved.
180-day data center and BESS moratoria adopted July 6, 7-0 (Res. 7238, 7239), exempting approved projects. UDO Amendment #80 adopted Oct. 5, 6-0 (Ord. 19850): special use permit, setbacks and buffers for major facilities. Recall petitions against a council member; residents sued July 2 to block the recall election.
Phase 1 under construction. Bly Road rerouting by NorthPoint expected to finish fall 2026. Nebius: operational in 2027.
Stage gauge
- 1Land acquiredFrom NorthPoint, December 2025
- 2Chapter 100 approvalOrd. 19791, 5-2, March 2, 2026
- 3GroundbreakingMay 12, 2026
- 4Phase 1 constructionOperational in 2027, per Nebius
- 5Initial power200 MW; IPL targets 2H 2026
- 6PILOT paymentsExpected to begin 2028
- 7800 MWIPL study for added power by early 2029
- 81.2 GW campusFour buildings; 400 MW on-site generation under evaluation
By the numbers
The campus sits in NorthPoint Development’s roughly 1,200-acre EastGate Commerce Center in eastern Independence, land the city rezoned to mixed use in 2007 and to business park and industrial use in 2022, with Little Blue Parkway built between 2008 and 2013. The Chapter 100 plan describes multiple buildings totaling about 2.1 million square feet; the city’s FAQ says up to four buildings and about 2.5 million square feet. Cooling is closed-loop with a propylene glycol and water mix, filled once at about 1 million gallons per 200 MW building and replenished about 20 percent a year, against a Courtney Bend treatment plant average of 28 million gallons a day. Each building carries two diesel emergency generators with 6,200-gallon tanks, run only to power down during outages and about an hour a month for testing. Noise walls of 12 and 15 feet surround chillers and dry coolers.
Timeline
- 2022EastGate area rezoned to business park and industrial use; NorthPoint buys the land.City FAQ
- December 2025Nebius acquires about 398 acres from NorthPoint.Nebius / City FAQ
- Dec. 8, 2025Council study session on EastGate.City FAQ
- Jan. 12, 2026Nebius open house and council study session.City FAQ
- Feb. 16, 2026Public hearing on taxable industrial development revenue bonds for the Nebius Project at M-78 and Little Blue Parkway.Council agenda
- March 2, 2026Council approves the Chapter 100 plan and bonds, Ord. 19791, 5-2.Council agenda / cover sheet
- May 12, 2026Groundbreaking with ARCO National Construction; Gov. Kehoe and NVIDIA’s Ned Finkle quoted; Nebius pays off school meal debt and signs an MCC agreement.Nebius release
- May 13, 2026Nebius Group tells shareholders the 1.2 GW Missouri site is expected to be operational in 2027.6-K
- July 2, 2026Three residents sue to block the Sept. 1 recall election against Councilmember Perkins, Case 2616-CV22087.Petition as filed
- July 6, 2026Council adopts 180-day moratoria on new data center and BESS applications, 7-0; approved projects exempt.Council agenda
- July 14, 2026Planning Commission takes up UDO Amendment #80, data centers and BESS.Staff report
- Oct. 5, 2026Council adopts Ord. 19850, 6-0: special use permit, setbacks and buffers for major data centers; entitled projects exempt.Council agenda
- 2H 2026IPL target for initial power.Nebius project page
- 2027Site expected to be operational.6-K
- 2028PILOT payments expected to begin.City FAQ
- 2046Abatement term ends.Cover sheet
Sources
- City of Independence — Regular City Council Meeting, March 2, 2026: Ord. 19791, agenda item cover sheet, plan, leases and performance agreements
- City of Independence — City Council Regular Meeting, Feb. 16, 2026: public hearing on the Nebius Project bonds
- City of Independence — Regular City Council Meeting, July 6, 2026: Res. 7238 and 7239 (moratoria)
- City of Independence — Regular City Council Meeting, Oct. 5, 2026: Ord. 19850 (UDO Amendment #80) and Planning Commission staff report
- City of Independence — Nebius Data Center FAQs
- Nebius — Nebius secures approval for its first gigawatt-scale AI factory (March 3, 2026)
- Nebius — Nebius breaks ground on gigawatt-scale AI factory in Independence, Missouri (May 12, 2026)
- Nebius — Nebius x Independence, Missouri project page
- Nebius Group N.V. — Form 6-K, Q1 2026 shareholder letter (May 13, 2026)
- Nebius Group N.V. — Form 6-K, Q2 2026 shareholder letter (Aug. 12, 2026)
- Nebius Group N.V. — Form 6-K, Q4 2025 shareholder letter (Feb. 12, 2026)
- Hurley et al. v. Holland et al., Petition for Declaratory Judgment and Injunctive Relief, Jackson County Circuit Court, 2616-CV22087 (July 2, 2026; copy hosted by Fox4)