Microsoft Fairwater
Buildout Tracker (beta): Microsoft’s Fairwater campus in Mount Pleasant, Wisconsin has its first facility running and a second due in 2028, with a seven-building Area 2 master plan before the village, a $5 million annual incentive redirected to the village and a residents’ noise lawsuit headed toward a settlement.
Microsoft Fairwater
Microsoft’s first Fairwater facility in Mount Pleasant has been fully operational since June 23, 2026, when the company said construction was finished ahead of schedule, equipment had come online in April and about 550 full-time employees were on site. A second facility is under construction immediately to the west, with completion scheduled for 2028 and about 800 full-time employees expected once it runs. The village’s Tax Incremental District No. 5 annual report, dated Sept. 14, 2026, puts the district’s incremental value at $3.19 billion as of Jan. 1, 2026 and says Microsoft submitted plans in early 2026 for additional data center development in Area II, began the first phase of that work in spring 2026 with substantial completion expected by the end of 2028, and began grading the North Area for development. On Sept. 22, Dewberry Engineers filed an “MKE Area 2 Site Master Plan” for the parcel between Durand Avenue, Braun Road and Hewitt Memorial Drive: seven data center buildings, two electrical substations and an office and storage building, with stormwater wet ponds to be approved by the Wisconsin DNR. The plan was on the Plan Commission’s Oct. 14 agenda as SP-26-11; the commission’s minutes have not been posted.
Microsoft is redirecting the $5 million annual development incentive it earned under its 2023 agreement with the village. The village announced Sept. 28 that $4.9 million will go to Mount Pleasant to reduce the tax levy starting in 2027 and to pay capital costs without borrowing, and $100,000 to the Racine County Economic Development Corp.; the Village Board will set the use of the first $4.9 million when it adopts the 2027 budget. The residents’ noise lawsuit, filed July 1 in the U.S. District Court for the Eastern District of Wisconsin, has reached a settlement in principle: on Sept. 22 the plaintiffs and Microsoft jointly told the court they had agreed on material terms and asked for a 90-day stay to finish a written agreement and a Rule 23 preliminary-approval motion. The terms have not been disclosed and no class has been certified. Microsoft’s own account of the noise, posted on its local community blog, traces a tonal hum to cooling fans running at high speed during startup; the company set fan-speed limits, added sound-reduction components and said June 18 that its monitoring showed the mitigations had resolved the issue, with short-term mitigation still in progress as of July 20.
Project status
Tracker update: Oct. 19, 2026Status board
Microsoft funds the campus directly: $3.3 billion for the first facility and $4 billion for the second, with an estimated $4.7 billion in local hyperscale construction spending in Wisconsin from 2024 to 2028. It is forgoing the $5 million annual TID No. 5 incentive it earned under its 2023 village agreement.
Area 2 Site Master Plan (SP-26-11, 12023 Durand Ave.) was before the Plan Commission Oct. 14; minutes not yet posted. The village says foundation permits for additional data centers south of Durand Avenue were issued by summer 2026. The state PSC approved We Energies’ Very Large Customer tariff with modifications April 24, 2026.
Ostergaard v. Microsoft (E.D. Wis. 2:26-cv-01169), a putative noise class action by residents of the area bounded by Braun Road, 90th Street, the railroad tracks and Durand Avenue. Parties filed a notice of preliminary settlement and joint motion to stay Sept. 22; a text-only order followed Sept. 23.
First facility finished ahead of schedule. Second facility holds its 2028 date; Area 2 substantial completion targeted for end of 2028 in the TID No. 5 report.
Stage gauge
- 1Announced$3.3 billion first facility, May 2024
- 2Construction startFirst phase, 2024
- 3Second facility announced$4 billion, Sept. 18, 2025
- 4Equipment onlineStartup activities, April 2026
- 5First facility operatingConstruction complete, June 23, 2026
- 6Second facilityUnder construction; completion 2028
- 7Area 2 master planSP-26-11; Plan Commission Oct. 14, 2026
- 8Area 2 and North Area buildoutArea 2 phase 1 by end of 2028; rest not dated
By the numbers
The first facility sits on about 315 acres of TID No. 5’s Area III that Microsoft bought from the village in 2023 for slightly more than $50 million; later agreements added about 1,000 acres covering the rest of Area III and most of Area II, with Microsoft guaranteeing $1.4 billion in additional property value by 2028. The village labels the operating facility Area 3B and the 2028 facility Area 3A. The Area 2 master plan covers the parcel bordered by Durand Avenue to the north, Braun Road to the south and Hewitt Memorial Drive to the west, zoned C-4 General Industrial. Microsoft says more than 90 percent of the first facility uses closed-loop liquid cooling filled once during construction, and that it is prepaying for the electrical infrastructure it uses. The AI Data Center Index lists the campus at “3.3 GW”; that figure matches the $3.3 billion first-facility cost, and Microsoft has not published a campus power figure.
Timeline
- May 2024Microsoft announces the $3.3 billion Mount Pleasant data center.Microsoft
- 2024Construction of the first phase begins on about 315 acres of Area III.TID No. 5 annual report
- Sept. 18, 2025Microsoft commits an additional $4 billion over three years for a second facility; first facility on track for early 2026.Microsoft
- Jan. 13, 2026Microsoft publishes its Community-First AI Infrastructure commitments, including paying its full share of local property taxes and supporting Wisconsin’s Very Large Customer rate structure.Microsoft
- Early 2026Microsoft submits plans for additional data center development in Area II; first phase of Area 2 construction begins in spring 2026, and grading begins in the North Area.TID No. 5 annual report
- April 2026Equipment comes online at the first facility. On April 15 Microsoft attributes a tonal hum reported by neighbors to the north to cooling fans at high speed and says it will cap fan speeds and add sound-reduction components.Microsoft
- April 24, 2026PSC approves We Energies’ Very Large Customer tariff with modifications: 15-year minimum term, 100 MW threshold, customers pay 100 percent of resource costs (docket 6630-TE-113).Wisconsin PSC
- June 18, 2026Microsoft says independent monitoring shows its mitigations fully resolved the hum; more sound-reduction components to follow.Microsoft
- June 23, 2026Construction of the first facility complete and fully operational; nearly 10,000 construction workers over two years; second facility under construction for 2028.Microsoft
- July 1, 2026Garret Ostergaard and David and Joy Wade of Sturtevant file a putative class action alleging private nuisance and negligence over noise; case assigned to Judge J.P. Stadtmueller.E.D. Wis. docket
- July 20, 2026Microsoft says short-term noise mitigation is still in progress and it continues to evaluate additional sound-reduction components.Microsoft
- Aug. 31, 2026Second amended complaint redefines the class area as the residential area bounded by Braun Road, 90th Street, the railroad tracks and Durand Avenue, “over 1,000 residential households.”E.D. Wis. Doc. 20
- Sept. 14, 2026TID No. 5 annual report: incremental value $3,191,691,500; Area 2 phase 1 substantial completion expected by end of 2028.Village / Ehlers
- Sept. 22, 2026Plaintiffs and Microsoft file a Notice of Preliminary Settlement and jointly move for a 90-day stay; a text-only order follows Sept. 23.E.D. Wis. Doc. 21
- Sept. 22, 2026Dewberry Engineers submits the MKE Area 2 Site Master Plan: seven data center buildings, two substations, one office and storage building.Plan Commission packet
- Sept. 28, 2026Village announces Microsoft is redirecting its $5 million annual incentive; Village President DeGroot presents the TID No. 5 incentive allocation to the Village Board.Village release / board minutes
- Oct. 14, 2026Plan Commission agenda: 12023 Durand Avenue Site Plan Review, SP-26-11.Village agenda
- October 2026Village staff to release a 2027 budget proposal with concepts for the first $4.9 million; next regular Village Board meeting Oct. 26.Village release / calendar
Sources
- Microsoft Source — Microsoft completes construction on first datacenter facility in Mount Pleasant, Wisconsin (June 23, 2026)
- Microsoft On the Issues — Made in Wisconsin: The world’s most powerful AI datacenter (Sept. 18, 2025)
- Microsoft Local Community — Update on our investigation of humming sound at our Mount Pleasant datacenter (April 3–July 20, 2026)
- Microsoft On the Issues — Building Community-First AI Infrastructure (Jan. 13, 2026)
- Village of Mount Pleasant — Mount Pleasant delivers tax relief after Microsoft foregoes incentives (Sept. 28, 2026)
- Village of Mount Pleasant — Village Board meeting minutes, Sept. 28, 2026 (item D.1)
- Village of Mount Pleasant / Ehlers — Annual Tax Incremental District Report, TID No. 5 (Sept. 14, 2026)
- Village of Mount Pleasant — Tax Incremental District No. 5 overview
- Village of Mount Pleasant — Plan Commission agenda, Oct. 14, 2026 (SP-26-11)
- Dewberry Engineers — Applicant narrative, MKE Area 2 Site Master Plan (Sept. 22, 2026)
- Public Service Commission of Wisconsin — PSC Overhauls We Energies’ Data Center Tariff (April 24, 2026)
- Ostergaard v. Microsoft Corp., No. 2:26-cv-01169 (E.D. Wis.) — Class Action Complaint (July 1, 2026)
- Ostergaard v. Microsoft Corp. — Second Amended Complaint (Aug. 31, 2026)
- Ostergaard v. Microsoft Corp. — Notice of Preliminary Settlement and Joint Motion to Stay Proceedings (Sept. 22, 2026)
- Ostergaard v. Microsoft Corp. — Docket via CourtListener (RECAP)
- Village of Mount Pleasant — Village Board meeting, Oct. 26, 2026 (calendar)