News
INNIO’s $8 Billion Backlog Shows Data Center Power Orders Are Still Coming; Will Expand U.S. Production

Amid industry questions about debt, financing, and the future of the data center buildout, one thing is clear: orders keep coming in.
Data center power provider INNIO reported that it now has an $8 billion equipment order backlog, up 142 percent from a year earlier. The Munich-based maker of gas engines (which has a U.S. presence based in Wisconsin) booked $2.2 billion in equipment orders during the third quarter, up 10 percent year over year, while data center deliveries helped lift revenue to a company record.
The company also raised its revenue forecast for 2026.
The backlog grew by about $1.4 billion during the quarter even as deliveries rose to 1.2 gigawatts from 1.1 gigawatts a year earlier. Data centers accounted for 60 percent of the company’s third-quarter equipment revenue, executives said in releasing the company’s earnings.
Based on the company’s financials, data centers accounted for about $1.8 billion of the quarter’s $2.2 billion in equipment orders.
“I think we have still (have) a very strong pipeline. So I do not see any slowdown for the next years,” CEO Olaf Berlien said in a conference call Tuesday with financial analysts. He said he was discussing already customer projects for 2029, 2030 and 2031.
Company executives pointed to INNIO’s first quarter with more than $1 billion in revenue and a 21 percent adjusted EBITDA margin; Innio reported it was scaling production to meet demand for AI infrastructure after booking more than $6 billion in equipment orders during the first nine months of 2026. Each engine delivered also creates service revenue opportunities over its operating life, he said.
Overall, INNIO reported $1.17 billion in revenue, up 57 percent from the prior year, and $109.2 million in net income, up from $39.5 million. Adjusted earnings before interest, taxes, depreciation and amortization rose 70 percent to $245.4 million.
Equipment revenue climbed 86 percent to $777.6 million as the company converted older orders into deliveries. For the first nine months, net income fell to $83.3 million from $136.9 million; the company cited $93.6 million in IPO and public market readiness costs.
Its equipment backlog includes compression and other power applications as well as data centers. The company books an equipment order only when it has a signed contract with a defined scope, fixed price, delivery schedule and fully defined terms, a low probability of cancellation, completed approvals and risk reviews, and any required down payment in hand. The company reported that most equipment orders have take-or-pay provisions, down payments and cancellation fees.
INNIO booked a 620-megawatt follow-on order from a leading data center developer it did not name, adding to 1.1 gigawatts ordered in the second quarter.
Executives also reported a service agreement for the first 500 megawatts of previously ordered capacity, covering major overhauls that could extend the engines into a second operating life. Separately, Liberty Energy ordered 450 megawatts of behind-the-meter power equipment for North American data center projects, with delivery scheduled for 2028.
The company’s CFO Berlien said in prepared remarks that average U.S. grid connection waits have grown from less than two years in 2000-2007 to more than six years today. INNIO sells on-site systems that can be installed in modules, adding generation as a campus grows. He said the engines can respond to rapid changes in AI computing load and keep running after a grid connection arrives, as backup during grid disruptions.
He also pointed to low water use as an advantain water-constrained areas. The company says its Type 6 engines use less than 0.1 liter of water per megawatt-hour, compared with about 200 liters for the turbines it compared them against.
Berlien said that INNIO is highly selective when choosing customers. The company prioritizes customers with long-term offtake agreements with hyperscalers or frontier AI labs, or a clear path to such agreements, he said. INNIO had allocated no meaningful volume to neocloud operators, Berlien said.
Data center sales leader Martin Widner told analysts that INNIO usually does not work with land developers and seeks a back-to-back contract, or a clear path to one, with the end customer, typically a hyperscaler.
He said the company has never worked with neoclouds on slot reservations or firm orders.
INNIO reported about 19 gigawatts across equipment backlog and slot reservations, up from more than 15 gigawatts the previous quarter. That combined measure includes future production slots that have not yet become equipment orders.
Executives told analysts that they will convert into orders between six and 18 months from now, depending on the reserved delivery timing.
Reservations are already signed for 2029, 2030 and 2031, and capacity for 2029 and 2030 remains available as it is released, Innio reported
The company raised its 2026 revenue forecast to $3.9 billion to $4 billion and its adjusted EBITDA forecast to $780 million to $800 million. It expects to deliver about 1.5 gigawatts of power equipment in the fourth quarter, taking the full-year total to about 4.5 gigawatts.
To support deliveries, INNIO is expanding production at its Jenbacher and Waukesha, Wisconsin-based operations. It recently assembled its first Jenbacher generator at the Waukesha site and plans to increase annual capacity from 3.5 gigawatts in 2025 to more than 10 gigawatts by 2030. Management said it would release production slots in stages tied to that ramp.