Buildout Tracker (beta): Homer City Energy Campus, Indiana County, Pa. — a 4.5 GW gas-fired power campus under construction on the former coal plant site, with an Amazon Data Services plan for 39 data center buildings on about 2,200 acres now under a 90-day county review and the air permit under appeal.
Homer City Energy Campus
Homer City Redevelopment announced on April 2, 2025 that it would turn Pennsylvania’s largest former coal plant into a gas-fired power campus of up to 4.5 gigawatts, with Kiewit Power Constructors as engineering, procurement and construction contractor, seven GE Vernova 7HA.02 turbines, financing led by Knighthead Capital Management, more than $10 billion for initial power infrastructure and site readiness, construction starting in 2025 and first power by 2027. EQT signed a non-binding agreement in principle on July 15, 2025 to be the exclusive gas supplier, up to 665,000 MMBtu a day from the Texas Eastern and Eastern Gas Transmission systems. The Pennsylvania Department of Environmental Protection issued Air Plan Approval 32-00457A on Nov. 18, 2025, covering seven combined-cycle turbines with duct burners and up to 10 Mitsubishi FT8 simple-cycle units, with facility-wide limits of 1,142.8 tons a year of NOx and 17.55 million tons of CO2-equivalent, after 573 public comments and a Sept. 17 hearing. Clean Air Council, PennFuture and the Sierra Club appealed the approval to the Environmental Hearing Board on Dec. 17, 2025, arguing among other things that DEP failed to review the data center campus as part of the project. In its Oct. 20, 2026 update, Homer City Generation said more than 2,000 tradespeople are on site, vertical construction began in April, demolition and excavation finished in June ahead of schedule, the first two heat recovery steam generators are installed and the first gas turbine has been set on its foundation.
The data center half of the project reached the county record on Aug. 28, 2026, when Amazon Data Services, Inc. submitted a preliminary land development plan titled “PIT100 Masterplan” to the Indiana County Planning Commission. The applicant’s narrative describes 39 data center buildings of about 225,000 square feet each on roughly 2,200 acres across six sites in Center and Black Lick townships, built in phases from December 2026 to a full build-out in mid-2036, with 1,500 to 2,000 permanent operations staff, electricity from FirstEnergy supported by the 4.5 GW plant, non-contact cooling water drawn under existing withdrawal rights and returned to the station for reuse, and AWS paying for the new electrical infrastructure. The Planning Commission accepted the plan for review on Oct. 14, setting the official filing date and a 90-day review that runs to Jan. 12, 2027, and the county commissioners the same day hired Gibson-Thomas Engineering, with subconsultants for architecture and for noise and vibration, to review the plan at the applicant’s expense. The county is separately amending its subdivision and land development ordinance for large industrial projects, having received 248 written comments by Aug. 12, and residents have spoken on the data centers at every commissioners’ meeting since: 17 on Sept. 9, three on Sept. 23 and five on Oct. 14. Gov. Josh Shapiro’s Executive Order 2026-05, signed Aug. 18, removes AI data centers from the state’s Permit Fast Track program and conditions DEP review on a binding commitment to the state’s GRID requirements and local approval.
Project status
Tracker update: Oct. 29, 2026Status board
Knighthead Capital Management leads project financing for the power campus; no amount, lenders or closing disclosed. AWS says it will pay for the electrical infrastructure serving its campus; its investment figure is not stated.
DEP air plan approval (Nov. 18, 2025), Title V renewal (Feb. 26, 2026) and Chapter 102 authorizations issued; NPDES amendment and renewal pending. County accepted the AWS land development plan Oct. 14; review runs to Jan. 12, 2027. No PJM or FirstEnergy interconnection filing for the data center load located.
Environmental Hearing Board appeal of the air permit by Clean Air Council, PennFuture and Sierra Club (Dec. 17, 2025). 573 DEP comments; 25 public commenters at four county meetings since Aug. 12; 248 written comments on the county’s SALDO amendment.
Demolition and excavation finished June 2026 ahead of schedule, per Homer City Generation. First power still stated for 2027.
Stage gauge
- 1Announced4.5 GW campus, April 2, 2025
- 2Gas supplyEQT agreement in principle, July 15, 2025
- 3Air permitDEP Plan Approval 32-00457A, Nov. 18, 2025
- 4Permit appealEHB, filed Dec. 17, 2025
- 5Plant constructionVertical from April 2026; first turbine set
- 6Data center planCounty review to Jan. 12, 2027
- 7First power2027, per Homer City Redevelopment
- 8Data center build-outDec. 2026 to 2036, per applicant
By the numbers
The 3,200-acre former Homer City Generating Station sits in Center and Black Lick townships, with existing transmission ties to PJM and NYISO, substations and water access carried over from the coal plant. The DEP-permitted power block comprises seven GE 7HA.02 combined-cycle turbines rated at 3,515 MMBtu/hr each with 1,034 MMBtu/hr duct burners, ten 301 MMBtu/hr simple-cycle turbines, three auxiliary boilers and seven cooling towers; the permit requires 369 tons a year of VOC emission reduction credits before operation. The AWS plan spreads 39 buildings across six sites named Bruner, Helen, Green, West, Harvey/Gaston and Rura, phased so that Rura and West start in December 2026 and Helen finishes last in 2036. Water for the data centers would come from the plant’s existing withdrawal rights and planned treatment facilities and be returned to the station for reuse.
Timeline
- April 2, 2025Homer City Redevelopment and Kiewit announce the 4.5 GW gas-powered campus: seven GE Vernova 7HA.02 turbines, Knighthead-led financing, more than $10 billion, first power by 2027.Homer City Redevelopment
- July 15, 2025EQT agreement in principle for up to 665,000 MMBtu a day; HCR says the campus is under construction.Homer City Redevelopment
- Sept. 17, 2025DEP public hearing on the air plan approval at IUP; comment period closes Sept. 29 with 573 comments.DEP comment response document
- Nov. 18, 2025DEP issues Plan Approval 32-00457A to Homer City Generation LP; expires May 31, 2027.Pennsylvania DEP
- Dec. 17, 2025Clean Air Council, PennFuture and Sierra Club appeal the plan approval to the Environmental Hearing Board.Notice of appeal
- Feb. 26, 2026DEP issues Title V operating permit renewal 32-00055.Pennsylvania DEP
- April 2026Vertical construction begins with the first structure on the campus.Homer City Generation
- June 2026Demolition and excavation complete ahead of schedule: 112,000 tons of scrap recycled, about 3 million cubic yards moved.Homer City Generation
- July 11, 2026DEP posts a second draft NPDES permit amendment; renewal and Outfall 027 applications pending.Pennsylvania DEP
- Aug. 12, 2026County commissioners report 248 written comments on a SALDO amendment for large industrial projects including data centers; a hearing is to be scheduled.County minutes
- Aug. 18, 2026Gov. Shapiro signs Executive Order 2026-05 on data centers: GRID requirements, local approval, no Permit Fast Track for AI data centers.Governor’s Office
- Aug. 28, 2026Amazon Data Services submits the PIT100 Masterplan preliminary land development plan: 39 buildings, about 2,200 acres, 2026–2036.ICOPD / applicant narrative
- Sept. 9, 2026Seventeen residents address the commissioners on the proposed data centers.County minutes
- September 2026First heat recovery steam generators arrive on site.Homer City Generation
- Oct. 14, 2026Planning Commission accepts the AWS plan for review; commissioners hire Gibson-Thomas Engineering for the review, 3-0, at the applicant’s expense.ICOPD / county minutes
- Oct. 20, 2026Homer City Generation: 2,000+ workers, first two HRSGs installed, first gas turbine set, zero OSHA recordables.Homer City Generation
- Nov. 18, 2026Planning Commission meeting with the AWS application on the agenda.ICOPD
- Jan. 12, 2027End of the 90-day county review period for the AWS plan.ICOPD
- 2027First power from the gas plant, per Homer City Redevelopment; air plan approval expires May 31, 2027.Homer City Redevelopment / DEP
Sources
- Homer City Redevelopment — Homer City Redevelopment and Kiewit Announce Country’s Largest Natural Gas-Powered Data Center Campus (April 2, 2025)
- Homer City Redevelopment — Agreement in Principle for EQT Corporation to Supply the Campus (July 15, 2025)
- Homer City Generation — Kiewit One-Year Anniversary On Site (Oct. 20, 2026)
- Pennsylvania DEP — Final Plan Approval 32-00457A, Homer City Generation LP (Nov. 18, 2025)
- Pennsylvania DEP — Comment Response Document, Plan Approval 32-00457A (Nov. 18, 2025)
- Pennsylvania DEP — Homer City Generation Site Redevelopment permit portal
- Clean Air Council, PennFuture and Sierra Club — Notice of Appeal to the Environmental Hearing Board, Plan Approval 32-00457A (Dec. 17, 2025)
- Indiana County Office of Planning & Development — Homer City Energy Campus / PIT100 Masterplan application status and Planning Commission schedule
- Amazon Data Services, Inc. — Project Narrative: Homer City Energy Campus (submitted with the PIT100 Masterplan; hosted copy)
- Indiana County Commissioners — Minutes, Oct. 14, 2026
- Indiana County Commissioners — Minutes, Sept. 23, 2026
- Indiana County Commissioners — Minutes, Sept. 9, 2026
- Indiana County Commissioners — Minutes, Aug. 12, 2026
- Office of Gov. Josh Shapiro — Executive Order 2026-05 on data centers (Aug. 18, 2026)