Google Project Tembo
Buildout Tracker (beta): Google’s Project Tembo near Cheyenne, Wyoming has its power lined up — Black Hills contracts for about 2.7 GW through 2048, a $4 billion AEP fuel-cell plant and Tallgrass turbines — while the state siting council hears the Black Hills plant expansion Nov. 9 and the rescoped four-building campus works through county permits.
Google Project Tembo
Black Hills Corp. disclosed Oct. 6 that it signed two definitive agreements with Google, effective Sept. 30, 2026 and running through 2048, to serve the planned data center near Cheyenne: a Large Power Contract Services Agreement and a Generation Facilities Agreement. Black Hills will supply up to 590 megawatts of grid-connected service, 564 MW of it from new company-owned gas generation at its Cheyenne Prairie Generating Station and 26 MW from market purchases and the industrial tariff, and will manage about 2.1 gigawatts of Wyoming third-party resources through a private microgrid under its Large Power Contract Service tariff, about 2.7 GW in all including reserve margins. Service starts in late 2027 and ramps to peak load in 2030. Black Hills plans $1.8 billion of generation capital spending from 2027 to 2029, with full recovery over the contract term, and Google has advanced $399 million in refundable payments for long-lead equipment, to be repaid by June 30, 2027. On Oct. 14, AEP said it will invest about $4 billion in a 702 MW Bloom fuel-cell plant near Cheyenne, owned by Cheyenne Fuel Cell, LLC, under a 20-year power purchase agreement with Google, with construction starting in 2026 and full operation by the end of 2028. Tallgrass and Mitsubishi Power had already allocated two M501JAC turbines, about 1,150 MW, to the first phase of the Cheyenne Power Hub inside the Switchgrass Industrial Park.
The campus itself was first approved under Crusoe. Laramie County’s July 8 memo to residents says Crusoe withdrew, that Google, doing business as Jupiter Star Holdings, is re-submitting the project as Project Tembo, and that the revised plan has four buildings instead of five, 3,080,000 square feet instead of 4,025,500, and a peak construction workforce of 2,500 instead of 5,000. The county is processing the site plan revision administratively; a Class B conditional use permit for the “Project Tembo HUB-1 Office Support Facility” east of the industrial park on U.S. 85 was postponed Aug. 13 at the applicant’s request and returned to the Planning Commission’s Sept. 10 agenda, for which minutes have not been posted. On the power side, the Wyoming Industrial Siting Council will hear Black Hills’ application to expand Cheyenne Prairie from 140 MW to 692 MW, with three simple-cycle turbines and 24 reciprocating engines, on Nov. 9; the plant’s air permit was approved in August, the Robinson substation certificate in May, and transmission filings for a new 230 kV substation and lines (Sept. 11) and a large-customer transmission cost mechanism (July 7) are before the Public Service Commission, with a further transmission certificate due in the fourth quarter. No organized opposition appears in the county or state records reviewed.
Project status
Tracker update: Oct. 21, 2026Status board
Black Hills: $1.8 billion generation capex 2027–2029, contracts through 2048 with full capital recovery; $399 million advanced by Google. AEP: about $4 billion, 20-year PPA. Google’s own campus spending is not disclosed in any direct source.
Approved: Robinson substation CPCN (May), CPGS air permit (August). Pending: Industrial Siting permit DEQ/ISC 25-05 (hearing Nov. 9), PSC transmission CPCN 20003-278-EN-26 and LCTCAM tariff 20003-273-EM-26, a Q4 transmission CPCN, and the county HUB-1 office CUP (PZ-26-00057).
No objections appear in the county minutes or state notices reviewed. The Nov. 9 Industrial Siting Council contested-case hearing is the formal venue; party-status requests have been accepted since Aug. 12.
Crusoe withdrew as applicant. The plan dropped from five buildings and 4.03 million sq. ft. to four buildings and 3.08 million sq. ft.; the office CUP hearing was postponed Aug. 13.
Stage gauge
- 1AnnouncedCrusoe–Tallgrass 1.8 GW campus, July 24, 2025
- 2County land-use approvalsPUD zone change and site plan under Crusoe; Tallgrass Power Hub
- 3Developer changeGoogle re-submits as Project Tembo, July 2026
- 4Power contractsBlack Hills LPCSA and GFA, effective Sept. 30, 2026
- 5On-site generation dealsTallgrass turbines (May 15); AEP fuel cells (Oct. 14)
- 6State siting and PSCISC hearing Nov. 9; transmission CPCNs pending
- 7Campus permitsSite plan revision administrative; HUB-1 CUP pending
- 8Power service beginsLate 2027, per Black Hills; peak load 2030
By the numbers
The campus adjoins the Switchgrass Industrial Park in Laramie County, where Tallgrass is building the gas-fired Cheyenne Power Hub fed by its Rockies Express Pipeline. The HUB-1 office support facility would sit directly east of the industrial park on Tracts 1 and 2 of the Cold Creek Buffalo Company Subdivision, adjacent to U.S. 85, with two permanent entrances. Black Hills’ new generation goes on the existing Cheyenne Prairie Generating Station site; AEP’s fuel cells are described only as “near Cheyenne.” Black Hills’ agreements include cost pass-throughs, early-termination provisions and collateral requirements that it says keep data center costs off existing customers.
Timeline
- July 24, 2025Crusoe and Tallgrass announce a 1.8 GW AI data center campus in southeast Wyoming, designed to scale to 10 GW.Tallgrass
- 2025–2026Laramie County approves a zone change to the Switchgrass Industrial Park PUD and a commercial site plan for Crusoe, and zone change and site plan for Tallgrass’ Power Hub.Laramie County memo
- May 15, 2026Tallgrass and Mitsubishi Power allocate two M501JAC turbines, about 1,150 MW, to Phase 1 of the Cheyenne Power Hub; investment more than $7 billion.Tallgrass
- May 2026PSC approves the Robinson substation CPCN.Black Hills 8-K
- June 30, 2026Black Hills asks the Industrial Siting Division to amend the Cheyenne Prairie permit for three turbines, 140 MW to 260 MW (DEQ/ISC 11-04).Wyoming DEQ
- July 7, 2026PSC notices Cheyenne Light, Fuel and Power’s Large Customer Transmission Cost Adjustment Mechanism filing, docket 20003-273-EM-26.Wyoming PSC
- July 8, 2026County commissioners tell residents Google, as Jupiter Star Holdings, is re-submitting the former Project Jade as Project Tembo; Crusoe has withdrawn; four buildings, 3.08 million sq. ft.Laramie County
- July 14, 2026Industrial Siting Division notices Black Hills’ application to expand Cheyenne Prairie from 140 MW to 692 MW (DEQ/ISC 25-05); hearing set for Nov. 9.Wyoming DEQ
- August 2026Air quality permit for the Cheyenne Prairie expansion approved.Black Hills 8-K
- Aug. 13, 2026Planning Commission postpones the HUB-1 office CUP hearing 3-0 at the applicant’s request; a site plan amendment is in process.Planning Commission minutes
- Sept. 10, 2026HUB-1 office CUP (Case 26-465) and a Project Tembo item (Case 26-466, HDR Engineering) on the Planning Commission agenda; minutes not posted.Planning Commission agenda
- Sept. 11, 2026PSC notices a CPCN for a 230 kV substation, a 115 kV line and 230 kV lines, docket 20003-278-EN-26, the South Cheyenne transmission expansion.Wyoming PSC / Black Hills 8-K
- Sept. 30, 2026Black Hills–Google Large Power Contract Services Agreement and Generation Facilities Agreement take effect, terms through 2048.Black Hills 8-K
- Oct. 6, 2026Black Hills announces the agreements: 2.7 GW resource mix, $1.8 billion capex, $399 million Google advances, service late 2027.Black Hills 8-K
- Oct. 14, 2026AEP announces a 702 MW, about $4 billion fuel-cell project near Cheyenne under a 20-year PPA with Google; full operation by end of 2028.AEP
- Oct. 30 / Nov. 9, 2026Industrial Siting Council pre-hearing and contested-case hearing on the Cheyenne Prairie expansion, Cheyenne.Wyoming DEQ
- Q4 2026Black Hills to file a Wyoming transmission expansion CPCN; Cheyenne Prairie construction to begin.Black Hills 8-K / Wyoming DEQ
- Late 2027Power service to the data center begins; AEP fuel cells fully operating by end of 2028; peak load 2030.Black Hills 8-K / AEP
Sources
- Black Hills Corp. — Form 8-K Exhibit 99.1, Black Hills Corp. Executes Definitive Agreements to Serve Google’s Planned Data Center in Cheyenne, Wyoming (Oct. 6, 2026)
- Black Hills Corp. — Investor relations release (Oct. 6, 2026)
- AEP — AEP Advances Innovative Energy Solution for Google with 702MW of Bloom Fuel Cells (Oct. 14, 2026)
- Tallgrass — Tallgrass and Mitsubishi Power Americas Announce Turbine Allocation for Cheyenne Power Hub (May 15, 2026)
- Tallgrass — Crusoe and Tallgrass Announce AI Data Center in Wyoming (July 24, 2025)
- Laramie County Board of Commissioners — Project Tembo Data Center memo to residents (July 8, 2026)
- Laramie County — Project Tembo Data Center Site Plan and Conditional Use Permit public notice
- Laramie County Planning Commission — Minutes, Aug. 13, 2026
- Laramie County Planning Commission — Agenda, Sept. 10, 2026
- Wyoming DEQ Industrial Siting Division — Courtesy public notice, Cheyenne Prairie Generating Station Expansion Project, DEQ/ISC 25-05 (July 14, 2026)
- Wyoming DEQ Industrial Siting Division — Courtesy notice, Black Hills permit amendment request, DEQ/ISC 11-04 (July 9, 2026)
- Wyoming DEQ — Comment portal and application, Cheyenne Prairie Generating Station Expansion Project 25-05
- Wyoming Public Service Commission — Public notices (dockets 20003-273-EM-26, 20003-278-EN-26 and related)