UpdatedFriday, November 6, 2026

Data Centers

Data center buildout adds to construction strains as other spending falls, industry group says

The data center buildout is adding pressure on construction materials, equipment and skilled labor while masking declines in other private construction spending, the Associated General Contractors of America said Monday in a new report.

Its analysis of a Census Bureau report showed total construction spending fell 1.9 percent from August and 2.7 percent from September 2025.

Data center construction spending rose 90 percent in September from a year earlier and 8.6 percent from August. Private electric power spending increased 14 percent over the year. Together, the two categories accounted for the gains in private nonresidential construction, where spending on all other categories combined fell 7.8 percent over 12 months.

“Surging demand for data centers and power projects is masking cutbacks in other investments …” said Ken Simonson, the association’s chief economist. He said data center and power demand was worsening the supply and pricing problems stemming from high tariffs and international conflicts.

The group’s Construction Inflation Alert says data center demand is intensifying competition for materials, skilled workers and equipment as contractors also contend with tariffs, higher petroleum costs and immigration enforcement that makes qualified workers harder to find.

By late September, some steel fabricators had reserved all capacity through the first quarter of 2027 or longer. Some contractors reported warnings that they would receive as little as one-fourth of the beams they had contracted for. Other fabricators were turning down new customers.

Nonresidential construction input prices rose 11.9 percent over the year through September, compared with a 3.7 percent rise in consumer prices, AGC reported.

Transformers, switchgear and generators also face long delivery times, threatening timely project completion. AGC said manufacturers’ capacity additions could take years to satisfy demand for steel beams and electrical gear.

The workforce survey conducted in July and August 2026 by AGC and the National Center for Construction Education and Research included responses from more than 1,000 firms with job openings. Electricians were the hardest craft workers to find: 81 percent of firms with openings listed those positions as hard to fill. Worker shortages were the most frequently cited reason for project delays, reported by 42 percent of respondents.

Construction spending totaled a seasonally adjusted annual rate of $2.19 trillion. Private nonresidential spending rose 2.3 percent over the year. Private residential construction declined 8.9 percent, while public construction increased 1 percent.

Beyond AGC’s national figures, construction continues at campuses in Louisiana, Texas and Missouri. Meta’s Richland Parish data center in Louisiana is under construction and will house its Hyperion AI cluster, with planned investment exceeding $50 billion and a target of 5 gigawatts of computing capacity. Meta and the state expect about 7,500 workers at peak construction. The project began as a $10 billion development announced in December 2024. Meta and the state outlined the larger campus in July, with nearly 10 million square feet planned.

Entergy, the utility serving Meta’s Richland Parish campus, is seeking approval for power infrastructure to support the campus expansion. Its application in docket U-37882 proposes seven gas units totaling 5,278 megawatts, batteries and transmission. Louisiana Public Service Commission consideration is scheduled for Dec. 16, with consumer and environmental groups contesting the proposal. Regulators approved three Entergy gas plants in August 2025, and construction began on two in December 2025.

In Abilene, Texas, Crusoe’s Stargate campus is operating for Oracle and OpenAI while delivery continues across eight buildings. Oracle reported in September that six buildings representing 618 megawatts had been delivered. The full campus is planned for 1.2 gigawatts, financed through a $15 billion joint venture involving Crusoe, Blue Owl Capital and Primary Digital Infrastructure.

Crusoe has also announced a separate 900-megawatt campus for Microsoft on adjacent land, with its first building expected to receive power in mid-2027.

In Independence, Missouri, Nebius broke ground in May on a campus with capacity of up to 1.2 gigawatts across four buildings on roughly 400 acres. The company gives a five-to-seven-year construction timeline. Its power plan calls for 800 megawatts through Independence Power & Light from a new plant at the retired Blue Valley site and 400 megawatts of on-site generation, still under evaluation.

AGC urged federal officials to enact a new highway and transit funding bill, lower tariffs and provide a mechanism for contractors to add skilled workers. The association said uncertainty over funding and rising costs were weighing on investment across several construction categories.

AGC said demand for steel beams and electrical gear was unlikely to ease unless data center construction dropped off.